Tetley Hall Block ELCA0001-011LME  ·  C & AJ Marshall

Contract value
£537,730
net of MC discount, inc VO1 to VO10
Value certified
£430,456
80.1% of contract, Apps 1 to 6
Cost to date
£270,631
all trades to date
Forecast gross profit
£183,923
34.2% margin
Net payment due
£61,292
Application 6, after retention

Latest snapshot  ·  August 2026

August 2026 report →

80.1%complete by value certified

Application 6 certifies £430,456 of the £537,730 contract, 80.1% by value. Cost to date is £270,631, so the job is forecast to finish at £183,923 of gross profit, a 34.2% margin, with £61,292 due on the application after retention.

Contract value
£0£537,730
Source: August 2026 performance report. The figures in the ribbon above are as reported there; the bar is complete by value certified.

Contract

In progress
ClientC & AJ Marshall
Contract typeM&E Subcontract
Project refLCA0001-011LME
Contract value£537,730
Forecast margin34.2%
Latest reportAugust 2026