Project performance report  ·  May 2026  ·  Application 3

Tetley Hall Block E

M&E Subcontract  ·  Leodis Developments Ltd

Project ref

LCA0001-011LME

Client

C & AJ Marshall

Contract value

£527,084

Value certified

£205,564

Status

In progress

Contract value

£527,084

Net of MC discount, inc 5 confirmed VOs

Value certified

£205,564

39.0% complete by value

Cost to date

£94,474

26.5% of forecast cost

Forecast margin

32.3%

£170,439 provisional

Net payment due

£98,131

Application 3, after retention

Percent complete — value certified vs cost incurred39.0% vs 26.5%
Value certified Cost incurred Future works Cost to complete
Value certified 39.0% of contract · cost incurred 26.5% of forecast costIndicative gross profit earned £111,090Forecast gross profit £170,439

At Application 3, valued to the end of May 2026, the contract is 39.0% complete by value certified but only 26.5% by cost incurred. Billing is running well ahead of cost, a healthy cash position, and on a summary basis the work done has earned an indicative £111,090 of gross profit so far. The application values this period at £103,296, leaving £98,131 due after retention. On the cost side, with provisional electrical costs now included the forecast final cost is £356,646 and the forecast margin 32.3%, against a priced 31.7%. The job is therefore forecasting essentially on budget, a little ahead, though that conclusion rests on the provisional electrical figures and should be read as such until they are confirmed.

1

Performance forecast

Priced vs forecast at completion

This is how the job was priced set against where it is now forecast to land. The contract was tendered to return £166,959 of gross profit at 31.7%. On current costs, including the provisional electrical placeholders, it is forecast to deliver £170,439 at 32.3%, a favourable movement of £3,479. The chart shows where that movement comes from trade by trade.

Priced gross profit

£166,959

31.7% on £527,084

Forecast gross profit

£170,439

32.3% — provisional forecast

Gross profit variance

+£3,479

+0.7 pts vs price · favourable

Forecast summary

Contract value£527,084.17
Priced cost budget£360,124.70
Forecast final cost£356,645.60
Cost variance vs budget£3,479.10 under
Cost incurred to date£94,474.16
Cost to complete£262,171.44
Forecast gross profit£170,438.57
Forecast margin32.3%
Value recovered per £1 of cost£1.48

Gross profit movement by trade

Cost saving, gross profit upCost overrun, gross profit down

Net movement +£3,479. Trades with no movement are omitted, and the electrical bar rests on provisional costs.

2

Commercial position

Application 3

Application 3 values the works at £103,296 for the period, taking cumulative certified value to £205,564, or 39.0% of the adjusted contract. After five percent retention of £5,165, the net payment due on this application is £98,131. A further £322,073 of measured works remains to be valued in future applications.

Application history

ApplicationGrossRetentionNet
Application 1£25,139.37£1,256.97£23,882.40
Application 2£77,128.99£3,856.45£73,272.54
Application 3£103,295.75£5,164.79£98,130.97
Cumulative£205,564.11£10,278.21£195,285.91

Position summary

Contract value (gross)£532,289.41
Main contractor discount(£13,307.24)
Variations (VO1 to VO6)£8,654.50
Adjusted contract value£527,636.67
Cumulative value certified£205,564.11
Future measured works£322,072.56
Retention held to date£10,278.21
Net payment due this application£98,130.97

The adjusted contract value follows the application and includes the contingent VO6 (£552.50); the headline contract value above excludes it pending client acceptance, hence the small difference between the two.

3

Cost and margin position

Priced vs forecast by trade

The bridge below sets the priced cost and margin for each trade against the forecast. Plumbing and heating and electrical carry the largest scope; the electrical position is the one still firming up as forward parts costs are confirmed. The charts split cost incurred from cost to complete and show where the remaining forecast spend sits.

TradeContract valuePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating £165,697£119,86027.7% £101,80938.6% +10.9 pts
HVAC £51,968£34,00034.6% £39,20024.6% -10.0 pts
Electrical provisional £225,967£146,95335.0% £156,32530.8% -4.1 pts
Preliminaries £18,000£6,00066.7% £6,00066.7% +0.0 pts
Subcontracted £70,658£51,76226.7% £51,76226.7% +0.0 pts
Full contract£527,084£360,12531.7%£356,64632.3%+0.7 pts

Cost incurred vs cost to complete

Cost to dateCost to complete

Priced cost vs forecast cost by trade

Priced costForecast cost
4

Value against cost

Earned position

This is the view the two workbooks unlock together. The work certified to the client stands at 39.0% of the contract, while cost incurred is 26.5% of the forecast final cost. Value is running ahead of cost, which is favourable for both cash and margin, and indicates an indicative gross profit earned of £111,090 on the work done to date. For every £1 of cost spent so far, £2.18 of value has been certified. Because the contract lines and the cost lines are structured differently, this is a summary comparison rather than a line by line reconciliation.

A word of caution on why value is running ahead of cost. The gap is not purely outperformance on margin. It also reflects how this period was billed. The HVAC works met an issue on site that needed rectifying, which effectively halted progress on that package while cost continued to be incurred, and to balance the application additional progress was claimed elsewhere to lift the amount billed. The application also includes the additional basement screed variation, which has been applied for ahead of the client signing it off. Beyond that, the percentage complete is assessed from the number of plots finished with an element of judgement, so there is a margin of error in the certified figure. Taken together, the indicative gross profit earned and the billing position are best read as a favourable but partly timing driven snapshot rather than secured margin, and the gap is likely to narrow as cost catches up, the screed variation is resolved, and progress is reassessed.

Percent complete — value vs cost

Indicative gross profit earned to date

£111,090

Value certified £205,564 less cost to date £94,474. Gross of discount and retention.

Billing position

12.5 pts

Value certified ahead of cost incurred, partly a timing position as set out above.

5

Discipline summary

P&H · HVAC · Electrical

The contract and the cost model do not share a common line structure, so the two are reconciled here at discipline level. Contract value and value certified are taken from the application; cost to date, forecast cost and forecast margin from the cost model. HVAC is the MVHR package; preliminaries and the combined design package sit within plumbing and heating, so that split is indicative rather than exact.

DisciplineContract valueValue certified% completeCost to dateForecast costForecast margin
Plumbing & Heating£242,225£122,95050.8%£50,524£159,57137.3%
HVAC£51,968£28,58255.0%£17,100£39,20024.6%
Electrical£238,097£57,40624.1%£25,300£156,32530.8%
6

Margin movement by trade

Confirmed lines

The chart compares priced margin against forecast margin for each trade. The two tables below pull out the individual lines moving against the price, drawn only from lines with confirmed costs. Containment has eroded from 35.0% to 17.8% on a parts overspend and the in house MVHR works from 34.6% to 24.6%, while above ground drainage and sanitaryware are forecasting ahead of price.

Priced vs forecast margin by trade

Priced margin %Forecast margin %

Lines eroding against price

LineValuePriced marginForecast marginMovement
Distribution Board and Consumer Unit£19,48835.0%16.4%-18.6 pts
Containment£11,38035.0%17.8%-17.2 pts
MVHR & Ventilation£51,96834.6%24.6%-10.0 pts

Lines improving against price

LineValuePriced marginForecast marginMovement
Above Ground Drainage & Lagging£36,21311.1%37.0%+25.9 pts
Sanitaryware / Pipework£44,17514.5%29.1%+14.6 pts
Domestic Water Services£18,86437.4%48.0%+10.6 pts
Communal Distribution Pipework£20,06922.3%23.3%+1.0 pts

Provisional electrical lines and lines without cost pricing (10 Vanquish Mirrors, Data Rack & Wifi, Testing & Commissioning, Demonstrations and Training) are excluded from these tables.

7

Variations register

VO1 to VO6
VariationValueStatus
VO1 — Basement screed£1,850Confirmed
VO2 — Wiring for fire rated windows£686Confirmed
VO3 — Fire alarm£419Confirmed
VO4 — Access control£4,285Confirmed
VO5 — CCTV£862Confirmed
VO6 — Additional basement screed contingent£552.50In application, acceptance unconfirmed

VO6 has been entered into Application 3 at £552.50 but is not yet confirmed by the client and is excluded from the headline contract value. If declined, the cost would fall to be settled between Leodis and the underfloor heating contractor.

8

Risks and data completeness

May 2026

Forecast rests on provisional electrical costs

The remaining electrical costs are placeholders set at each line's remaining cost budget, totalling £95,625 of forecast cost across 10 lines. They are not confirmed until actual prices are received from Jonny Brockett, and the outcome could move the forecast margin in either direction. Until then the priced margin of 31.7% is the reliable reference.

Owner: Commercial — action: obtain actual electrical costs from Jonny Brockett and refresh the forecast

Margin erosion on live lines

Containment has fallen to 17.8% and the in house MVHR works to 24.6% against price, on confirmed actuals rather than estimates. These should be reviewed against the remaining scope on those trades.

Owner: Operations — action: review parts procurement against budget

Value certified running ahead of cost

Certification at 39.0% against cost at 26.5% is favourable for cash, but part of it is timing rather than secured margin, reflecting the HVAC rectification, the screed variation claimed before sign off, and the margin of error in percentage complete. It also means future applications carry proportionally more cost. The position should be monitored so the late stage of the job does not erode the margin earned early.

Owner: Commercial — action: monitor cost to value as the programme matures

Items without cost pricing

10 Vanquish Mirrors, Data Rack & Wifi, Testing & Commissioning, Demonstrations and Training carry a contract value but no priced cost, so they are flagged in the schedule and excluded from the margin analysis to avoid a false full margin reading.

Owner: Commercial — action: enter cost pricing for these lines

Contingent variation VO6

The additional basement screed is in the application at £552.50 but unconfirmed by the client. If declined, liability sits between Leodis and the underfloor heating contractor.

Owner: Commercial — action: confirm client position, then agree liability if rejected

LineContract valuePriced costCost to dateForecast costForecast margin
Plumbing & Heating
Incoming Water Services£1,917£1,600£0£1,60016.5%
Communal Distribution Pipework£20,069£15,600£12,200£15,40023.3%
Hot Water Cylinders / Thermal Stores£24,269£12,600£0£12,60048.1%
Domestic Water Services£18,864£11,800£7,000£9,80048.0%
Sanitaryware / Pipework£44,175£37,760£3,550£31,30029.1%
10 Vanquish Mirrors no cost data£5,130£0£0£0100.0%
Above Ground Drainage & Lagging£36,213£32,200£6,000£22,80937.0%
Kitchen 1st & 2nd Fix£6,575£4,800£0£4,80027.0%
Testing & Commissioning£7,835£2,700£0£2,70065.5%
Demonstrations and Training£650£800£0£800-23.1%
HVAC
MVHR & Ventilation£51,968£34,000£17,100£39,20024.6%
Electrical
1st Fix Cabling provisional£76,948£51,800£15,950£45,35041.1%
Containment£11,380£7,397£9,350£9,35017.8%
Distribution Board and Consumer Unit£19,488£12,667£0£16,30016.4%
Earthing and Boarding provisional£950£618£0£65031.6%
Lighting & Emergency Lighting provisional£21,681£14,093£0£16,89322.1%
External Lighting provisional£15,138£9,840£0£11,64023.1%
Small Power provisional£19,108£12,420£0£15,22020.3%
Supplies to Mechanical Services provisional£2,875£1,869£0£2,00030.4%
Fire Alarm provisional£14,847£9,651£0£11,65121.5%
Access Control provisional£5,444£3,539£0£3,53935.0%
CCTV provisional£6,666£4,333£0£4,33335.0%
Services Identification provisional£657£428£0£30054.3%
EV Chargers£19,085£12,000£0£12,00037.1%
Data Rack & Wifi no cost data£650£0£0£0100.0%
Towel Rails (Inc Install)£7,700£6,300£0£6,30018.2%
Testing & Commissioning no cost data£2,700£0£0£0100.0%
Demonstrations and Training no cost data£650£0£0£800-23.1%
Preliminaries
Preliminaries£18,000£6,000£0£6,00066.7%
Subcontracted
Design£18,000£14,000£7,000£14,00022.2%
Dry Riser Installation£4,896£3,000£3,000£3,00038.7%
Underfloor Heating£47,762£34,762£11,774£34,76227.2%
RefDescriptionContract value% completeValue certified
Mechanical
3.13.1Preliminaries and Conditions of Contract£18,000.0045.0%£8,100.00
3.13.2Design£8,000.0090.0%£7,200.00
3.13.3Production of Design and Construction/Installation Working Drawings£3,000.000.0%£0.00
3.13..4Incoming Water services£1,917.000.0%£0.00
3.13.5Heating£47,762.0090.0%£42,985.80
3.13.7Internal Communal Riser Distribution Pipework£20,069.0080.0%£16,055.20
3.13.9Hot Water Cylinders/Thermal Stores£24,269.180.0%£0.00
3.13.10Domestic Water services£18,864.0065.0%£12,261.60
3.13.11MVHR Supply and Extract ventilation£51,967.5655.0%£28,582.16
3.13.16Sanitary Pipework (Inc. Sanitaryware Supply)£44,175.0025.0%£11,043.75
3.13.17Dry Riser Installation£4,895.67100.0%£4,895.67
3.13.19Testing and Commissioning£7,835.000.0%£0.00
3.13.20Demonstrations and Training£650.000.0%£0.00
3.13.22Core soil & waste, lagging of pipes£36,213.0050.0%£18,106.50
3.13.23Kitchen 1st and 2nd fix£6,575.0035.0%£2,301.25
Electrical
3.14.2Design£7,000.0090.0%£6,300.00
3.14.7Distribution Board and Consumer Unit Installation£19,488.000.0%£0.00
3.14.8Sub Mains Cabling£7,837.00100.0%£7,837.00
3.14.9Earthing and Bonding£950.000.0%£0.00
3.14.10Containment Installation£11,380.0090.0%£10,242.00
3.14.11Lighting & Emergency Lighting Installation£38,751.0022.5%£8,718.98
3.14.12External Lighting Installation£27,705.0010.0%£2,770.50
3.14.13Small Power Installation£34,154.0022.5%£7,684.65
3.14.14Supplies to Mechanical Services Installation£5,150.0060.0%£3,090.00
3.14.15Fire Alarm Installation including supplies, containment, cabling installation, interface, with the Automatic Opening Ventilator natural smoke vent system.£26,540.0022.5%£5,971.50
3.14.16Access Control System/Video Intercom Installation£9,740.0022.5%£2,191.50
3.14.17CCTV Installation£11,930.0015.0%£1,789.50
3.14.18IRS TV Installation£0.00£0.00
3.14.19BT Telecommunications Internal Cabling£900.0090.0%£810.00
3.14.20Virgin Media TV/Telecommunications Internal Cabling£0.00£0.00
3.14.21Services Identification£657.000.0%£0.00
3.14.22Testing and Commissioning£2,700.000.0%£0.00
3.14.23Demonstrations and Training£650.000.0%£0.00
3.14.25Electrical Vehicle Charger and Power Supplies£19,085.000.0%£0.00
3.14.26Data rack and wifi£650.000.0%£0.00
3.14.29Supply - Rointe 300 watt D series towel rails£6,500.000.0%£0.00
3.14.30Wire and Install£1,200.000.0%£0.00
3.14.3110 Vanquish Mirrors£5,130.000.0%£0.00
Variations
VO1 | Basement Screed£1,850.00100.0%£1,850.00
VO2 | Wiring for Fire Rated Windows£686.000.0%£0.00
VO3 | Fire Alarm£419.000.0%£0.00
VO4 | Access Control£4,285.000.0%£0.00
VO5 | CCTV£862.000.0%£0.00
VO6 | Additional Basement Screed£552.50100.0%£0.00
LCA0001-011LME  ·  Prepared May 2026  ·  Confidential  ·  Forecast figures provisional pending actual electrical costs