Project performance report  ·  June 2026  ·  Application 4

Tetley Hall Block E

M&E Subcontract  ·  Leodis Developments Ltd

Project ref

LCA0001-011LME

Client

C & AJ Marshall

Contract value

£530,951

Value certified

£280,230

Status

In progress

Director's summary · June 2026

At a glance

Behind programme

Forecast profit

£181,264

34.4% · up £10.8k on May

Payment due

£165,915

App 3 £98,131 due Jul · App 4 £67,784 due 22 Aug

Complete

52.8%

Revised finish Nov 2026

Labour efficiency

£328 a day

GP per labour day, above the £297 target rate

Certified by value 52.8%Cost incurred 48.4%

£280,230 certified · £250,721 of work still to bill

Profitability34.4% forecast, above tender
Cash positionBilling ahead of cost
ProgrammeSlipped from Sept to Nov
Resource useEfficient, spare capacity freed

Project manager's summary · June 2026

Progress and spend

On cost, MVHR to watch

Spend to date

£167,463

£1.67 recovered per £1 of cost

Cost to complete

£178,357

Forecast final cost £345,820

Labour days left

251.5

Across 5 months to Nov 2026

GP still to earn

£68,497

£13,699 a month

Trade progress by value

Plumbing & Heating63% complete
HVAC65% complete
Electrical42% complete

Most of the electrical value is still to come. The lines to keep under review are MVHR at a 17.0% forecast margin, and domestic water services and communal distribution pipework, both running past their cost budget. Pending variations VO6 to VO8 sit in the application awaiting client confirmation.

Where the job actually stands today: what has been certified, what has been spent so far, and the variations in play. Margins here are read as value recovered against cost, not profit locked in, since the trades have yet to close out.

Performance scorecard · to date

Spend to date

£167,463

cost incurred · 48.4% of final cost

Value certified

£280,230

52.8% of contract

Gross profit to date

£112,768

value certified less cost to date

Timing affectedBilling runs ahead of cost, so this leads the secured position; the job is forecast to finish at a 34.4% margin.
1

Commercial position

Application 4

Application 4 values the works at £71,352 for the period, taking cumulative certified value to £280,230, or 52.8% of the adjusted contract. After five percent retention of £3,568, the net payment due on this application is £67,784. A further £250,721 of measured works remains to be valued in future applications. Cost incurred to date stands at £167,463, so the work billed has recovered an indicative £112,768 above cost, a lead that is partly timing and narrows as the job progresses.

Application history

ApplicationGrossRetentionNet
Previous (Apps 1 to 3)£208,878.42£10,443.92£198,434.50
Application 4£71,352.06£3,567.60£67,784.46
Cumulative£280,230.48£14,011.52£266,218.96

Position summary

Base contract value (gross)£532,289.41
Main contractor discount(£13,307.24)
Variations (VO1 to VO8)£11,968.81
Adjusted contract value£530,950.98
Cumulative value certified£280,230.48
Future measured works£250,720.50
Retention held to date£14,011.52
Net payment due this application£67,784.46

Two contract values are in play: the cost model carries the five confirmed variations at £527,084, while the application adjusted value of £530,951 includes all eight, with VO6 to VO8 still to be confirmed. The variations register below has the full list.

2

Cost incurred to date

Actual spend vs budget

Of the £345,820 forecast final cost, £167,463 has been spent, so the job is 48.4% through its cost while 52.8% certified by value. The left panel sets each trade's cost budget against how far it has progressed; the right sets what each trade has spent against what it still has to spend. Every trade has spent less of its cost budget than its progress, electrical most of all, whose parts heavy second fix sits later in the programme.

Cost budget spent vs progress, by trade

Plumbing & Heating47% spent · 63% done
HVAC53% spent · 65% done
Electrical25% spent · 42% done

Bar is the share of each trade's cost budget spent; the mark is progress. Bar short of the mark means under budget for the stage. Electrical reads furthest under because its parts heavy second fix sits later.

Cost incurred vs cost to complete

Cost to dateCost to complete
3

Cost variances banked to date

Cost mostly incurred

These are the lines far enough through their spend that the variance is booked rather than forecast. First fix cabling, above ground drainage and containment have come in well under their priced cost, while domestic water services and communal pipework have run over. A little over half of the job's favourable movement against price is already banked here; the rest still rests on the forecast, shown in the forecast tab.

Lines eroding, cost banked

LineValuePriced marginForecast marginMovementCost spent
Domestic Water Services£18,86437.4%21.2%-16.2 pts81%
Communal Distribution Pipework£20,06922.3%13.8%-8.5 pts83%

Lines improving, cost banked

LineValuePriced marginForecast marginMovementCost spent
Containment£11,38035.0%68.5%+33.5 pts94%
Above Ground Drainage & Lagging£36,21311.1%32.2%+21.1 pts89%
1st Fix Cabling£76,94832.7%51.6%+19.0 pts88%

Cost spent is the share of each line's forecast final cost already incurred. Above 80% the margin movement is effectively locked, so these lines will not swing far from here.

4

Resource used to date

Labour consumed vs output

Gross profit earned

£112,768

£28,192 a month over four months

Fair share at target

£89,504

33% of the labour, valued at target

Above fair share

+£23,264

126% of its share of the target

Gross profit per labour day

£375
Break even £209 Target £297

Each of the 301 labour days drawn since March has returned £375 of gross profit, well clear of the £209 break even rate and the £297 target rate the whole business runs to.

Weight it draws vs return it covers

Share of labour capacity used33%
Break even overhead covered59%
Profit target covered42%

Draws 33% of the labour over the four months on site but covers 59% of the £190,000 break even overhead for the period. Profit target for the period £270,000.

Capacity used by trade · monthly

Electrical24 of 95 days · 26% used
Plumbing & Heating33 of 95 days · 35% used
HVAC18 of 38 days · 49% used

Average monthly days over the four months on site, against each trade's monthly capacity. Source: priced vs actual cost model, days used column.

MeasureAnnualMonthly
Resource share of capacity11.0%33.1%
GP vs break even19.8%59.4%
GP vs profit target13.9%41.8%
TradeDays usedUsed / mthCapacity / mth% monthly% annual
Plumbing & Heating130.532.694.634.5%11.5%
HVAC73.518.437.848.6%16.2%
Electrical97.024.294.625.6%8.5%
Trades301.075.2227.033.1%11.0%
Gross profit to date£112,768
Monthly GP average£28,192
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500
5

Variations register

VO1 to VO8
VariationValueStatus
VO1 — Basement screed£1,850.00Confirmed
VO2 — Wiring for fire rated windows£686.00Confirmed
VO3 — Fire alarm£419.00Confirmed
VO4 — Access control£4,285.00Confirmed
VO5 — CCTV£862.00Confirmed
VO6 — Additional basement screed contingent£552.50In application, cost pending
VO7 — Additional cameras new£416.00In application, acceptance unconfirmed
VO8 — Kensa pipework new£2,898.31In application, 0% valued this period

VO6 to VO8 are in Application 4 but not yet confirmed by the client on both value and cost. VO6 continues to carry a cost in the model (£300) with no matching charge, so if declined that cost would fall to be settled between Leodis and the underfloor heating contractor. The five confirmed variations are in the cost model contract value; the three pending ones are not.

What the remaining work is expected to require and return over the five months to November, and the risks that could move the forecast before the job closes out.

Performance scorecard · remaining work

Cost to complete

£178,357

spend still to come

Value still to earn

£246,854

contract value remaining

Gross profit to earn

£68,497

27.7% margin

+0.2 pts vs 27.5% tenderThe remaining work is priced close to tender, so most of the margin upside on the job is already banked in the work done. A further £3,867 of pending variations sits outside this until confirmed.
1

Resource requirement vs output profit

Forward · 5 months to Nov 2026

Gross profit still to earn

£68,497

£13,699 a month over five months

Fair share at target

£74,785

22% of the labour, valued at target

Against fair share

(£6,288)

92% of its share of the target

Gross profit per labour day

£272
Break even £209 Target £297

Each of the 251.5 labour days still to come returns £272 of gross profit, above the £209 break even rate but short of the £297 target rate. Electrical is the tightest single call at a quarter of its capacity, in line with it being the strongest profit per day trade.

Weight it draws vs return it covers

Share of labour capacity used22%
Break even overhead covered29%
Profit target covered20%

Draws 22% of the labour over the five months to November but covers 29% of the £237,500 break even overhead for the period, so it still returns more overhead than the labour it uses. Profit target for the period £337,500.

Capacity used by trade · monthly

Electrical24 of 95 days · 25% used
Plumbing & Heating20 of 95 days · 21% used
HVAC7 of 38 days · 18% used

Filled shows the days Tetley needs each month; the rest is spare for other work. Figures are trade labour only. Total capacity is 2,724 days a year (P&H 1,135, Electrical 1,135, HVAC 454). Break even overhead is £570,000 a year; the profit target adds £240,000.

MeasureAnnualMonthly
Resource share of capacity9.2%22.2%
GP vs break even12.0%28.8%
GP vs profit target8.5%20.3%
TradeDays leftNeed / mthCapacity / mth% monthly% annual
Plumbing & Heating98.519.794.620.8%8.7%
HVAC35.07.037.818.5%7.7%
Electrical118.023.694.625.0%10.4%
Trades251.550.3227.022.2%9.2%
Remaining gross profit£68,497
Monthly GP contribution£13,699
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500
2

Cost variances still to come

Cost barely started

These lines have barely been started, so their movement against price still rests on the forecast rather than on spend. External lighting and the distribution board are the two to watch, both forecast well below their priced margin with almost all the cost still ahead; against them small power and sanitaryware are forecast to improve. Because the spend has not happened, any of these could still move before the job closes.

Lines eroding, cost still to come

LineValuePriced marginForecast marginMovementCost spent
External Lighting£15,13835.0%2.2%-32.8 pts0%
Distribution Board and Consumer Unit£19,48835.0%12.8%-22.2 pts1%

Lines improving, cost still to come

LineValuePriced marginForecast marginMovementCost spent
Small Power£19,10835.0%61.8%+26.8 pts0%
Sanitaryware / Pipework£44,17514.5%28.0%+13.5 pts25%

Cost spent is the share of each line's forecast final cost already incurred. With almost nothing spent, these movements are estimates and carry the most forecast risk, either way.

3

Risks and data completeness

June 2026

MVHR forecasting at a thin margin

The in house MVHR works are now forecasting at 17.0% on a final cost of £43,109 against a sell value of £51,968, having taken £25,109 of cost already at 65% complete. It is the thinnest live discipline on the job and any further cost would push the margin down materially.

Owner: Operations — action: review remaining MVHR labour and parts against the £18,000 left to spend

Electrical costs confirmed and favourable

The electrical prices that were provisional placeholders in May have now been received from Jonny Brockett and have come in below the priced budget across first fix cabling, containment, small power, lighting and fire alarm, lifting the electrical forecast margin to 44.1% and adding £21,043 of forecast gross profit. This removes the largest open item from the May report.

Owner: Commercial — action: hold the confirmed prices and monitor as the electrical works progress

Lines running past budget on cost

Domestic water services has already spent £12,061 against a priced budget of £11,800 and is forecast to finish at £14,861, taking its margin down to 21.2%. Communal distribution pipework is on a similar path at 13.8%. Both should be reviewed against the scope remaining.

Owner: Operations — action: review parts and labour on the mechanical distribution lines

Pending variations VO6 to VO8

VO6 additional basement screed, VO7 additional cameras and VO8 Kensa pipework total £3,867 and are in the application but not confirmed by the client. VO6 carries a cost with no matching charge, so if declined that cost sits between Leodis and the underfloor heating contractor.

Owner: Commercial — action: confirm client position on all three, then agree liability on VO6 if rejected

Items without cost pricing

10 Vanquish Mirrors and the electrical Testing and Commissioning line carry a contract value but no priced cost, so they are flagged in the schedule and excluded from the margin analysis to avoid a false full margin reading.

Owner: Commercial — action: enter cost pricing for these lines

The current position and the forecast for the remainder combined into a single view of how the job is expected to finish against the price.

Performance scorecard · at completion

Forecast final cost

£345,820

£36,066 under budget

Contract value

£527,084

cost model basis

Forecast gross profit

£181,264

34.4% margin

+6.9 pts vs 27.5% tenderThe whole job view: performance to date plus the forecast for the remainder.
1

Performance forecast

Priced vs forecast at completion

This is how the job is now priced set against where it is forecast to land. The priced cost budget has been revised up this period, mainly on MVHR, so the priced margin now reads 27.5% and returns £145,199 of gross profit. On current costs, with the electrical prices confirmed, it is forecast to deliver £181,264 at 34.4%, a favourable movement of £36,066. The chart shows where that movement comes from trade by trade.

Priced gross profit

£145,199

27.5% on £527,084

Forecast gross profit

£181,264

34.4% — electrical costs confirmed

Gross profit variance

+£36,066

+6.8 pts vs price · favourable

Cost bridge

Priced cost budget£381,885.61
Forecast final cost£345,820.01
Cost variance vs budget£36,065.60 under
Cost incurred to date£167,462.97
Cost to complete£178,357.04
Value recovered per £1 of cost£1.52

Gross profit movement by trade

Cost saving, gross profit upCost overrun, gross profit down

Net movement +£36,066, led by electrical and plumbing and heating forecasting ahead of the priced budget. Subcontracted works show no movement and are omitted.

2

Cost and margin position

Priced vs forecast by trade

The table below sets the priced cost and margin for each trade against the forecast. Electrical is now the strongest performer as its confirmed prices have come in below the priced budget, while HVAC is the thin trade at 17.0%. By discipline, plumbing and heating is around 63% complete and HVAC 65%, but electrical only 42%, so most of the electrical value is still to come. The tables beneath pull out the individual lines moving against the price.

TradeContract valuePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating £165,697£119,86027.7% £106,62835.6% +7.9 pts
HVAC £51,968£47,0009.6% £43,10917.0% +7.4 pts
Electrical £225,967£147,40334.8% £126,36044.1% +9.3 pts
Preliminaries £18,000£6,00066.7% £7,50058.3% -8.4 pts
Subcontracted £70,658£57,53818.6% £57,53818.6% +0.0 pts
Full contract£527,084£381,88627.5%£345,82034.4%+6.8 pts

Lines eroding against price

LineValuePriced marginForecast marginMovement
External Lighting£15,13835.0%2.2%-32.8 pts
Distribution Board and Consumer Unit£19,48835.0%12.8%-22.2 pts
Domestic Water Services£18,86437.4%21.2%-16.2 pts
Communal Distribution Pipework£20,06922.3%13.8%-8.5 pts

Lines improving against price

LineValuePriced marginForecast marginMovement
Containment£11,38035.0%68.5%+33.5 pts
Small Power£19,10835.0%61.8%+26.8 pts
Above Ground Drainage & Lagging£36,21311.1%32.2%+21.1 pts
1st Fix Cabling£76,94832.7%51.6%+19.0 pts
Sanitaryware / Pipework£44,17514.5%28.0%+13.5 pts

First fix cabling, above ground drainage and containment are cost backed, with actual cost already incurred. Small power and external lighting have not yet started on site, so their movement rests on the forecast estimate rather than confirmed spend.

3

Resource across the whole job

Labour used and to come vs output

Forecast gross profit

£181,264

£20,140 a month over nine months

Fair share at target

£164,290

27% of the labour, valued at target

Above fair share

+£16,974

110% of its share of the target

Gross profit per labour day

£328
Break even £209 Target £297

Across the full nine months each labour day returns £328 of gross profit, clear of the £209 break even rate and the £297 target rate the whole business runs to.

Weight it draws vs return it covers

Share of labour capacity used27%
Break even overhead covered42%
Profit target covered30%

Draws 27% of the labour over the nine months but covers 42% of the £427,500 break even overhead for the period. Return runs ahead of the resource consumed. Profit target for the period £607,500.

Capacity drawn by trade · monthly

Electrical24 of 95 days · 25% used
Plumbing & Heating25 of 95 days · 27% used
HVAC12 of 38 days · 32% used

Average monthly days over the nine months from March to November, against each trade's monthly capacity. Whole job days are 229 plumbing and heating, 108.5 HVAC and 215 electrical, 552.5 across the trades.

MeasureAnnualMonthly
Resource share of capacity20.3%27.0%
GP vs break even31.8%42.4%
GP vs profit target22.4%29.8%
TradeDaysUsed / mthCapacity / mth% monthly% annual
Plumbing & Heating229.025.494.626.9%20.2%
HVAC108.512.137.831.9%23.9%
Electrical215.023.994.625.3%18.9%
Trades552.561.4227.027.0%20.3%
Forecast gross profit£181,264
Monthly GP average£20,140
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500
LineContract valuePriced costCost to dateForecast costForecast margin
Plumbing & Heating
Incoming Water Services£1,917£1,600£0£1,60016.5%
Communal Distribution Pipework£20,069£15,600£14,307£17,30713.8%
Hot Water Cylinders / Thermal Stores£24,269£12,600£400£12,20049.7%
Domestic Water Services£18,864£11,800£12,061£14,86121.2%
Sanitaryware / Pipework£44,175£37,760£7,800£31,80028.0%
10 Vanquish Mirrors no cost data£5,130£0£0£0100.0%
Above Ground Drainage & Lagging£36,213£32,200£21,767£24,56032.2%
Kitchen 1st & 2nd Fix£6,575£4,800£0£1,50077.2%
Testing & Commissioning£7,835£2,700£500£2,00074.5%
Demonstrations and Training£650£800£0£800-23.1%
HVAC
MVHR & Ventilation£51,968£47,000£25,109£43,10917.0%
Electrical
1st Fix Cabling£76,948£51,800£32,610£37,21051.6%
Containment£11,380£7,397£3,390£3,59068.5%
Distribution Board and Consumer Unit£19,488£12,667£200£17,00012.8%
Earthing and Boarding£950£618£0£9005.3%
Lighting & Emergency Lighting£21,681£14,093£0£9,00058.5%
External Lighting£15,138£9,840£0£14,8002.2%
Small Power£19,108£12,420£0£7,30061.8%
Supplies to Mechanical Services£2,875£1,869£0£2,00030.4%
Fire Alarm£14,847£9,651£0£6,50056.2%
Access Control£5,444£3,539£0£4,50017.3%
CCTV£6,666£4,333£0£3,60046.0%
Services Identification£657£428£0£41037.6%
EV Chargers£19,085£12,000£0£12,00037.1%
Data Rack & Wifi£650£450£0£45030.8%
Towel Rails (Inc Install)£7,700£6,300£0£6,30018.2%
Testing & Commissioning no cost data£2,700£0£0£0100.0%
Demonstrations and Training no cost data£650£0£0£800-23.1%
Preliminaries
Preliminaries£18,000£6,000£1,100£7,50058.3%
Subcontracted
Design£18,000£14,000£7,000£14,00022.2%
Dry Riser Installation£4,896£3,000£3,000£3,00038.7%
Underfloor Heating£47,762£40,538£36,669£40,53815.1%
RefDescriptionContract value% completeValue certified
Mechanical
3.13.1Preliminaries and Conditions of Contract£18,000.0060.0%£10,800.00
3.13.2Design£8,000.00100.0%£8,000.00
3.13.3Production of Design and Construction/Installation Working Drawings£3,000.000.0%£0.00
3.13.4Incoming Water services£1,917.000.0%£0.00
3.13.5Heating£47,762.0090.0%£42,985.80
3.13.7Internal Communal Riser Distribution Pipework£20,069.0080.0%£16,055.20
3.13.9Hot Water Cylinders/Thermal Stores£24,269.185.0%£1,213.46
3.13.10Domestic Water services£18,864.0085.0%£16,034.40
3.13.11MVHR Supply and Extract ventilation£51,967.5665.0%£33,778.91
3.13.16Sanitary Pipework (Inc. Sanitaryware Supply)£44,175.0040.0%£17,670.00
3.13.17Dry Riser Installation£4,895.67100.0%£4,895.67
3.13.19Testing and Commissioning£7,835.0035.0%£2,742.25
3.13.20Demonstrations and Training£650.000.0%£0.00
3.13.22Core soil & waste, lagging of pipes£36,213.0075.0%£27,159.75
3.13.23Kitchen 1st and 2nd fix£6,575.0075.0%£4,931.25
Electrical
3.14.2Design£7,000.00100.0%£7,000.00
3.14.7Distribution Board and Consumer Unit Installation£19,488.000.0%£0.00
3.14.8Sub Mains Cabling£7,837.00100.0%£7,837.00
3.14.9Earthing and Bonding£950.000.0%£0.00
3.14.10Containment Installation£11,380.00100.0%£11,380.00
3.14.11Lighting & Emergency Lighting Installation£38,751.0050.0%£19,375.50
3.14.12External Lighting Installation£27,705.0025.0%£6,926.25
3.14.13Small Power Installation£34,154.0050.0%£17,077.00
3.14.14Supplies to Mechanical Services Installation£5,150.0060.0%£3,090.00
3.14.15Fire Alarm Installation including supplies, containment, cabling installation, interface, with the Automatic Opening Ventilator natural smoke vent system.£26,540.0050.0%£13,270.00
3.14.16Access Control System/Video Intercom Installation£9,740.0050.0%£4,870.00
3.14.17CCTV Installation£11,930.0040.0%£4,772.00
3.14.18IRS TV Installation£0.00£0.00
3.14.19BT Telecommunications Internal Cabling£900.0090.0%£810.00
3.14.20Virgin Media TV/Telecommunications Internal Cabling£0.00£0.00
3.14.21Services Identification£657.000.0%£0.00
3.14.22Testing and Commissioning£2,700.0035.0%£945.00
3.14.23Demonstrations and Training£650.000.0%£0.00
3.14.25Electrical Vehicle Charger and Power Supplies£19,085.000.0%£0.00
3.14.26Data rack and wifi£650.000.0%£0.00
3.14.29Supply - Rointe 300 watt D series towel rails£6,500.000.0%£0.00
3.14.30Wire and Install£1,200.0030.0%£360.00
3.14.3110 Vanquish Mirrors£5,130.0030.0%£1,539.00
Variations
VO1 | Basement Screed£1,850.00100.0%£1,850.00
VO2 | Wiring for Fire Rated Windows£686.0050.0%£0.00
VO3 | Fire Alarm£419.0050.0%£0.00
VO4 | Access Control£4,285.0050.0%£0.00
VO5 | CCTV£862.0050.0%£0.00
VO6 | Additional Basement Screed£552.50100.0%£0.00
VO7 | Additional Cameras£416.0050.0%£0.00
VO8 | Kensa Pipework£2,898.310.0%£0.00
LCA0001-011LME  ·  Prepared July 2026  ·  Projected costs to 30 June 2026  ·  Confidential