Director’s summary

At a glance · August 2026

Below price, recovering

Forecast profit

£207,436

29.6% · £28,818 below priced

Complete

51.3%

by value of work done · finish Dec 2026

Resource return

£317 a day

forecast gross profit per labour day, above the £297 target

August payment short

£50,252

£8,312 received against £58,563 due on the schedule

The margin has recovered. Forecast profit is £207,436 at 29.6%, up from £201,393 at 28.1% in July, because the electricians reforecast their remaining days down from 240 to 174 and HVAC came in cheaper. It is still 4.1 points below the 33.7% the job was priced at, and the whole of that gap is electrical. The three sources also agree on the contract value for the first time, at £700,780, which is £14,661 below the figure the July report used. The one thing that went the wrong way in August was cash: the client paid £8,312 against the £58,563 the schedule called for.

The job is earning again; the question is whether the client keeps to the payment schedule

Every operational measure improved in August. The electrical reforecast took 66 days out of the work still to come, and the whole job still makes £317 of gross profit for each day of labour against the £297 we aim for. The electrical work is assessed at 46% complete, though, against the 53.7% of its forecast days already used, which pushes more of the profit into the work still to come: £91,677 of the £207,436 is yet to be earned, at £364 a day. Against that, August was the first month the client missed the schedule, paying £8,312 of the £58,563 due. There is no cash strain yet, because the client has paid £429,822 against £359,223 of work done and £243,464 of cost, so we are holding £70,599 more than the job has earned. The exposure only turns the other way if the shortfall repeats. September is due £103,634 net, the ordinary instalment plus the August arrears, and that is the number to watch.

Position

RAG · value vs cost
Work done by value 51.3%Cost incurred 49.4%

£359,223 of work done · £341,556 still to bill · value is only 1.9 points ahead of cost now, and cash is ahead of both at 61.3%

Profitability29.6% forecast, 4.1 points under the price
Cash position£50,252 short in August, but £70,599 funded ahead
ProgrammeElectrical 46% done on 53.7% of its days · 252 days left
Resource use£317 a day, above the target rate
Performance · to dateWhere the job stands today: what the client has paid, what we have done, and what we have spent.Tab 1 of 3

Performance scorecard · to date

£359,223 of £700,780 done

The client has paid £429,822 net of VAT, which is £70,599 more than the work done and £186,358 more than the £243,464 we have spent. This job is paid on a fixed monthly schedule rather than against applications, and it carries no retention.

Cost model →51%Complete by value
Work done
Contract
£0£700,780
Received £429,822Scheduled to come £270,958Retention held None
Money in£429,822net of 5% VAT · 61.3% of contract
Money earned£359,223value of work done · 51.3%
Money spent£243,464cost to date · 49.4% of final cost

August fell short. The schedule called for £58,563 including VAT in August and £8,312 arrived on the 28th, leaving £50,252 unpaid. It does not bite yet, because the client is £70,599 ahead of the work done, but September now carries £103,634 net rather than the usual £55,775.

1

Money in, done and spent

As at 31 August 2026

The client has paid £451,313 including VAT, which is £429,822 net, or 61.3% of the contract. The value of the work done is £359,223, or 51.3%, and we have spent £243,464. Cash is ahead of both because this job is paid on a fixed monthly schedule agreed at the outset rather than against what has been valued, so the money arrives on a calendar rather than on progress. That leaves us holding £70,599 more than the job has earned and £186,358 more than it has cost, and there is no retention on this contract, so nothing is held back at the end. The one break in the pattern is August, when £8,312 came in on the 28th against £58,563 due.

Cash, value and cost against their base
Cash received61.3% of contract
Value of work done51.3% of contract
Cost incurred49.4% of forecast cost

Cash received and value done are shown against the £700,780 contract; cost is shown against the £493,344 we expect to spend in total. All figures are net of the 5% VAT this job carries.

Money position
Contract value£700,779.93
Value of work done£359,223.44
Received, net of VAT£429,822.06
Cost to date£243,464.41
Cash received ahead of work done£70,598.62
Cash received ahead of cost£186,357.65
Still to be paid, net of VAT£270,957.87

Receipts total £451,313.16 including VAT, being £443,001.66 to 20 August on the payment schedule and a further £8,311.50 on 28 August. The contract is £735,818.93 including VAT, which is £700,779.93 net at the 5% rate this job carries. Retention is none, so there is no cash tail after the final payment.

2

Progress and cost by trade

Completion vs spend

Progress this month is measured on labour days, not on the application

The August application was issued with its work complete column largely blank, showing nothing at all against the electrical work and nothing against the plumbing and HVAC variations, so it cannot carry the progress figure this month. For plumbing and heating and HVAC this report takes completion from the cost model instead, as the labour days used divided by the days the job is now forecast to take, giving 92.8% and 55.0%. Electrical is carried at the 46% assessed by Cal, which is below the 53.7% its labour days alone would give, so that trade is set behind where its hours put it. For the supply and subcontract packages, the utilities, the underfloor heating, the design and the preliminaries, which carry no labour days, the application’s own line assessment still stands and is used unchanged, with the Oldfield Lutron supply at the 20% shown on the agreed contract schedule. On that basis the job is 51.3% complete. It is not directly comparable with July’s 49.6%, which was measured on the application and against a larger contract value.

The job is 51.3% complete by value against 49.4% of the expected cost spent, so value is only 1.9 points ahead of cost, down from 4.0 points before the electrical assessment was applied. The bars below are all drawn to the same scale, so their length shows how big each cost group is, and the gold line marks each one’s budget. Three of the four are over budget rather than under. Electrical is £22,370 over and is the whole of the margin gap on this job; HVAC is £6,088 over; plumbing and heating is £360 over, which is nothing on a £81,237 trade. The other lump sum lines carry no movement at all in the model, priced and forecast at the same £195,859, which is itself worth a look given the Oldfield supply inside them is only 23% spent.

Forecast cost against budget, by trade

Plumbing & Heating

Budget £59,766 → forecast £60,126

£360 over£51,594 spent · 86% through

Electrical

Budget £115,505 → forecast £137,875

£22,370 over£54,023 spent · 39% through

HVAC

Budget £93,396 → forecast £99,484

£6,088 over£49,934 spent · 50% through

Other lump sum

Budget £195,859 → forecast £195,859

Level£87,913 spent · 45% through

£0£50k£100k£150k£200k

All four groups are on the same scale, so bar length shows the real size of the spend. The gold line is each group’s budget. Electrical is the one that matters: it is the largest overrun and it is only 39% spent, so most of it is still to come.

TradeDays usedDays leftDays at finishCompleteContract valueValue done
Plumbing & Heating129.0010.00139.0092.8%£81,237£75,393
Electrical201.75174.00375.7546.0%£194,203£89,333
HVAC71.0058.00129.0055.0%£179,637£98,870
Other lump sum—10.0010.0038.9%£245,703£95,628
Full contract401.75252.00653.7551.3%£700,780£359,223

The ten days against the other lump sum group are the testing and commissioning allowance, which has not started. Its 38.9% completion comes from the application’s line assessment, not from labour. Electrical is the one trade whose completion is not its own day count: at 46% it sits 7.7 points below the 53.7% its hours give, which is £14,939 of value. The trades used 50.5 days between them in August, electrical 28, plumbing and heating 12 and HVAC 10.5, and spent £20,751.

Forecast · remaining workWhat the work still to come needs and brings in: labour by trade, billing, profit and cash to finish, trade variances and the risks.Tab 2 of 3

Forecast scorecard · remaining work

£91,677 of gross profit still to earn

£341,556 still to bill against £249,879 still to spend, a 26.8% margin on what remains. Across the 252 labour days left that is £364 a day, well above the £209 we need to break even and the £297 we aim for. Forty four per cent of the job’s profit is still ahead of us.

Cash to completion →£364Gross profit per labour day left
Forecast £207,436
Priced £236,254
£0£236,254
Earned to date £115,759Still to earn £91,677Short of price £28,818
Cost to complete£249,879spend still to come
Labour days left252.0Sep to Dec 2026 · 174 of them electrical
Gross profit to earn£91,67726.8% · £364 a labour day

The profit is weighted to the work still to come. What is left makes £364 a day against the £288 earned so far, because the electrical assessment holds back value on a trade that has already spent its hours. Nearly half the job’s profit is still to be earned, so the outturn rides on how the remaining 174 electrical days actually run.

1

Cost to complete and remaining margin

Forward · to Dec 2026

Nearly half the profit is still ahead of us

There is £341,556 of work still to bill and £249,879 of cost still to spend, so what remains makes £91,677 of gross profit, a 26.8% margin. Across the 252 days of labour still to come that is £364 a day, well clear of the £209 we need to break even and the £297 we aim for. The work already done has earned £115,759 at £288 a day on a 32.2% margin, so the tail is set to earn better than the job has managed so far. That is the opposite of a job that banks its profit early, and it follows directly from holding electrical at 46% complete on 53.7% of its hours: the value that trade has not been credited with has to be earned later. Forty four per cent of the whole job’s profit now sits in front of us rather than behind, and it moves with the 174 electrical days that remain.

Remaining revenue

£341,556

work still to bill

Remaining cost

£249,879

spend still to come

Remaining gross profit

£91,677

26.8% · £364 a labour day

Where the remaining spend sits
Plumbing & Heating£8,532
Electrical£83,851
HVAC£49,550
Other lump sum£107,946
Cost to complete£249,879.27

Of the other lump sum spend, £73,477 is the Oldfield Lutron supply, which is the largest single cost still to land on this job and is only 23% spent.

Earned so far against still to earn
Gross profit earned to date£115,759 · £288 a day
Gross profit still to earn£91,677 · £364 a day
Short of the priced profit(£28,818)

The bars are shares of the £207,436 forecast profit, except the last, which is the £28,818 gap against the £236,254 the job was priced to make. The work still to come is set to earn at a better rate than the work already done.

2

Resource requirement to completion

Labour days by trade · Sep – Dec 2026

The job needs 252 more days of labour to finish, of which 174 are electrical, 58 are HVAC, ten are plumbing and heating and ten are the testing and commissioning allowance. The plumbing finishes in September as planned; HVAC and electrical run evenly to December. In August the electricians took 66 days out of their remaining forecast, from 240 down to 174, at the same time as working 28 days on site, which is the single reason the margin recovered this month. Spread across the four months to completion the electrical requirement is 43.5 days a month, a little over two electricians, which is 46% of what the firm can do in that trade in a month. That is comfortable on its own. It is not comfortable alongside Tetley Hall Block E, which needs 40 electrical days in September and 33 in October on its own August report. The two jobs together draw 88% of our electrical capacity in September and 81% in October.

TradeSepOctNovDecTotalPeak capacity
Plumbing & Heating10.0———10.011%
Electrical43.543.543.543.5174.046%
HVAC14.514.514.514.558.038%
Trade days68.058.058.058.0242.0

A further ten days sit on the testing and commissioning line, taking the total to 252. Peak capacity is the busiest month’s days set against what the firm can do in that trade in a month, being 94.6 days for plumbing and heating, 94.6 for electrical and 37.8 for HVAC. The even spread across September to December is a placeholder within the agreed completion date, not a programme; the project manager should confirm it.

This job alone · electrical

46% of capacity

43.5 days a month is a little over two electricians held on site from September to December. On its own that leaves better than half the trade free for everything else.

With Tetley Block E · September

88% of capacity

Tetley needs 40 electrical days in September and 33 in October. Added to this job that is 83.5 days in September against a capacity of 94.6, and 76.5 in October. Two jobs would take almost the whole trade for two months.

Share of firm capacity drawn · monthly peak
Plumbing & Heating (Sep)10 of 95 days · 11%
Electrical (Sep – Dec)43.5 of 95 days · 46%
HVAC (Sep – Dec)14.5 of 38 days · 38%
Electrical with Tetley (Sep)83.5 of 95 days · 88%

These figures feed the company wide resource plan, where they are added to every other live job against a capacity of 2,724 labour days a year. The last bar is the one to act on: two major jobs alone would take almost the whole electrical trade in September.

3

Billing, gross profit and cash to completion

Sep – Dec 2026

Cash on this job does not follow the billing. The client pays a fixed instalment of £58,563 including VAT, or £55,775 net, each month to December, agreed at the start and set out in the payment schedule prepared on 20 August. That makes the cash side of the forecast unusually firm: there is no application to argue over, no retention and no cash tail after December, and the last payment lands in the same month the work finishes. The only variable is whether the client pays. August is now £50,252 in arrears, so September carries £103,634 net if the arrears are recovered with the ordinary instalment. Against that, the work still to bill is £341,556 spread evenly across the four months in line with the labour, earning £91,677 of gross profit. All figures in this section are before VAT.

August arrears

£47,859

net of VAT · £50,252 including VAT

Cash to completion

£270,958

received Sep to Dec if the schedule holds

Retention drawn back

None

no retention on this contract, no cash tail

Work billed and gross profit by month

CostGross profit
£96.0k
£81.9k
£81.9k
£81.9k
SepOctNovDec

Each column is the work billed that month, with the cost at the bottom and the gross profit on top. September is larger because the last of the plumbing finishes in it. The profit stays level rather than tailing away, and at £364 a day it is better than the job has earned to date.

Cash received by month

Scheduled instalmentAugust arrears
£103.6k
£55.8k
£55.8k
£55.8k
SepOctNovDec

The instalment is the same every month by agreement. September carries the August arrears on top, which is the amber block. If those arrears are not recovered in September they push into October and the whole schedule slips a month past completion.

MonthWork billedCostGross profitCash due
September 2026£95,975£70,214£25,761£103,634
October 2026£81,861£59,888£21,973£55,775
November 2026£81,861£59,888£21,973£55,775
December 2026£81,859£59,889£21,970£55,775
Total remaining£341,556£249,879£91,677£270,958

Billing and cost are spread across the four months in proportion to the labour days each month carries, 68 days in September and 58 in each of the others; the monthly split is a guide, the total is firm, and December carries the rounding so the columns add up. Cash is the payment schedule of 20 August at £55,774.71 net a month, with the £47,859 of August arrears added to September. Monthly figures are rounded; totals are exact. All figures before VAT.

4

Cost variances by trade

Priced vs forecast · and since July

Every trade is now forecast to cost more than it was priced at, but the size of the difference is what matters. Electrical accounts for £22,370 of the £28,818 total, which is 78% of the whole gap, and it is the only trade where the movement is material. Its forecast now runs to 375.75 labour days against the 263 it was priced at. HVAC is £6,088 over on a mixture of days and materials, and plumbing and heating is £360 over, which is a rounding difference on that trade. The other lump sum lines show no movement at all, because the model carries the same figure for their priced and forecast cost. Since July the direction is favourable across the board: electrical gained 4.1 points as the remaining days fell from 240 to 174, plumbing and heating gained 7.7 points, and HVAC was flat. Note that the contract values moved as well this month, so the movement since July is directional rather than exact.

TradeChargePriced marginForecast marginMovementSince JulyCost spent
Plumbing & Heating£81,23726.4%26.0%(0.4 pts)+7.7 pts86%
Electrical£194,20340.5%29.0%(11.5 pts)+4.1 pts39%
HVAC£179,63748.0%44.6%(3.4 pts)(0.5 pts)50%
Other lump sum£245,70320.3%20.3%LevelLevel45%
Full contract£700,78033.7%29.6%(4.1 pts)+1.5 pts49%

Two adjustments are made to the model as supplied. The £700 cost saving on the skips line is carried into the forecast final cost, because the model applies the matching £1,050 charge reduction but leaves the cost out; without it the forecast cost reads £494,044 rather than £493,344. The main line of each trade is shown net of its variations, as the model books all of a trade’s cost against its main line.

Where the £28,818 gap against the price sits
Electrical(£22,370)
HVAC(£6,088)
Plumbing & Heating(£360)
Other lump sumLevel

Electrical is 78% of the shortfall against the price on its own. Fix the electrical labour forecast and the job is close to the margin it was sold at.

5

Risks and data completeness

August 2026

The client missed the August instalment by £50,252

The payment schedule called for £58,563 including VAT in August and £8,311.50 arrived on the 28th. This is the first month the schedule has not been met. It does not create a shortfall yet, because the client has paid £429,822 net against £359,223 of work done, so we are £70,599 ahead of what the job has earned and £186,358 ahead of what it has cost. The exposure only turns against us if the arrears are not recovered and the pattern repeats, at which point the buffer runs down at roughly £50,000 a month.

Owner: Commercial. Action: recover the £50,252 with the September instalment and confirm in writing that the schedule stands to December

Electrical is the whole of the margin gap and is only 39% spent

Electrical is forecast £22,370 over its cost budget, which is 78% of the £28,818 the job is short against its price. Its main line alone now forecasts 375.75 labour days against the 254 it was priced at, and that line is set to lose £3,690 against its £148,660 charge; the trade only reads 29% because £64,888 of electrical variations carry no cost of their own in the model. With 174 days still to run and only 39% of the cost spent, this is the number that decides the outturn. Every ten days added beyond the forecast is about £2,000 of labour, so the risk is a further reforecast rather than day rate drift.

Owner: Operations. Action: Lead Electrician to confirm the 174 remaining days and whether the review scope is genuinely inside them

Two jobs would take almost the whole electrical trade in September

This job needs 43.5 electrical days a month from September to December. Tetley Hall Block E needs 40 in September and 33 in October on its own August report. Together that is 83.5 days in September against a capacity of 94.6, or 88%, and 76.5 in October. Nothing else in the trade fits alongside those two, and the Tetley report already flags a further project starting in October that wants one or two electricians.

Owner: Operations. Action: set the September and October electrical plan across both jobs before the Tetley finish date is decided

The Oldfield Lutron supply is the largest untested cost left

The Oldfield Lutron supply is charged at £107,309 against a cost of £95,968, a margin of 10.6%, and only £22,491 of that cost has landed. £73,477 of supply is still to come on a line with £11,341 of margin in it, so an overrun of just over 15% on the remainder wipes the line out entirely. It is a supply order rather than labour, so it should be capable of being fixed rather than estimated.

Owner: Commercial. Action: confirm the Oldfield order value against the £95,968 carried in the model

The cost model prices remaining HVAC labour at a different rate from the forecast

The model’s remaining cost column runs £5,918 above the difference between its final cost and its cost to date, on plumbing and heating and HVAC. The cause is HVAC, where the remaining 58 days are priced at £250 a day in the remaining cost column while the final cost column carries them at £200. If the £250 is right, the forecast final cost is £499,262 and the profit falls to £201,518, a margin of 28.8% rather than 29.6%. This report uses the final cost column, which is what the model’s own margin is built on.

Owner: Finance. Action: Cal to set one labour rate for the remaining HVAC days and correct the model for September

The application does not carry progress this month, and its cover sheet is stale

The August application’s work complete column is blank against all of the electrical work and against the plumbing and HVAC variations, which is why completion is taken from labour days this month. Electrical does not use its own day count: it is carried at the 46% assessed by Cal rather than the 53.7% its hours give, which holds £14,939 of value back out of the work done and into the work still to come. That assessment should be confirmed with the site, because it is the difference between a job whose profit is evenly split and one with 44% of it still ahead. Its cover sheet is still headed Application Nr 4 with costs to 31 March 2026, the same stale header noted in July, and the file is the eighth in the sequence while July’s was recorded as Application 5, so the application number itself is unconfirmed. Separately, the model books all of a trade’s cost against its main line, so £86,105 of HVAC variations and £64,888 of electrical variations carry no cost of their own and read at a 100% margin; the trade subtotals are the only reliable level.

Owner: Finance. Action: Cal to confirm the 46% electrical assessment and its source, confirm the application number, and have the work complete column filled for September

Expected outcome · at completionWhere the job is now and the forecast for the rest, put together into one view of how it finishes against the price.Tab 3 of 3

Outcome scorecard · at completion

£207,436 forecast gross profit on £700,780

Priced to make £236,254 at 33.7%. On current costs it makes £207,436 at 29.6%, which is £28,818 short, and £22,370 of that shortfall is electrical. It is £6,044 better than the July forecast.

By trade →29.6%Forecast margin
Forecast 29.6%
Priced 33.7%
£0£236,254
Forecast gross profit £207,436Short of price £28,818
Forecast final cost£493,344costs to end August
Contract value£700,780all three sources agree
Forecast gross profit£207,43629.6% margin

4.1 points under the 33.7% price, and recovering. July’s forecast was 28.1%. The whole job view: where it is now plus the forecast for the rest, worked out as the value of the work less what it cost.

1

Priced vs forecast margin

At completion

The contract value now reconciles across all three sources

The July report used £715,441 from the balance and variations schedule, and noted that the cost model charged £716,750, an unreconciled difference of about £1,309. The August pack closes that. The cost model, the revised application schedule and the payment schedule all now carry £700,779.93 net, which the payment schedule states as £735,818.93 including VAT at 5%. That is £14,661 below the value the July report was built on, and it is the reason the contract value moves down this month while the profit moves up.

The job was priced to make £236,254 of gross profit at 33.7% on the £700,780 contract. On current costs it is forecast to make £207,436 at 29.6%, which is £28,818 short of the price. Every trade contributes something to that gap, but £22,370 of it is electrical alone. Against July, the position improved by £6,044 of profit and 1.5 points of margin, because the electrical remaining days fell from 240 to 174 and the HVAC final cost came down. The forecast final cost is £493,344 against a priced budget of £464,525, so the job recovers £1.42 for each £1 it spends.

Priced gross profit

£236,254

33.7% on the £700,780 contract

Forecast gross profit

£207,436

29.6%, costs over budget

Gross profit variance

(£28,818)

(4.1 pts) vs price · adverse

Cost bridge
Priced cost budget£464,525.47
Forecast final cost£493,343.68
Cost variance vs budget£28,818.21 over
Cost incurred to date£243,464.41
Cost to complete£249,879.27
Value recovered per £1 of cost£1.42
Movement since the July report
Contract value, lower by£14,661
Forecast final cost, lower by£20,705
Forecast gross profit, higher by£6,044
Forecast margin28.1% → 29.6%
Labour days at completion712.25 → 653.75
Gross profit per labour day£283 → £317

The contract value falls because the balance and variations figure the July report used is superseded by the reconciled £700,780. Costs fall further than the value does, so the profit rises. Each line is shown as the size of the move, with green marking a move in our favour.

2

Cost and margin by trade

Priced vs forecast
TradeChargePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating£81,237£59,76626.4%£60,12626.0%(0.4 pts)
Electrical£194,203£115,50540.5%£137,87529.0%(11.5 pts)
HVAC£179,637£93,39648.0%£99,48444.6%(3.4 pts)
Other lump sum£245,703£195,85920.3%£195,85920.3%Level
Full contract£700,780£464,52533.7%£493,34429.6%(4.1 pts)

Electrical is shown net of the £22,270 of intruder, fire and gate access savings, which the model books against that trade. Other lump sum groups the preliminaries and skips, testing and commissioning, design, the three utilities, the Oldfield Lutron supply, fire, intruder, CCTV, facial recognition and the underfloor heating. Only the skips are charged to the job under preliminaries; the rest of the prelim costs sit in company overheads.

The two trades that carry the job

HVAC and electrical are 53% of the contract between them and hold almost all of the risk left. HVAC is the better of the two, forecast at 44.6% against 48.0% priced, with 58 days and £40,000 of parts still to spend. Electrical is forecast at 29.0% against 40.5% priced, is only 39% spent, and has 174 days left. Plumbing and heating is effectively finished at 93% complete and lands on its price. The other lump sum group has no cost movement in the model at all, which is a modelling choice rather than a finding, and its largest line remains untested.

3

Resource across the whole job

Labour used and to come vs output · earned basis

Pays its way, but less well than it was priced to

Over the whole job it makes £317.30 of gross profit for every day of labour it uses. We need about £209 a day to cover our overheads and £297 a day to hit our profit target, so at £317.30 it clears both. It was priced to make £468 a day on 504.5 days, and it now takes 653.75 days, which is where the margin went. Over those 653.75 days it brings in £13,039 more gross profit than a job drawing that much of our labour would need to bring in to hit target.

Forecast gross profit

£207,436

on 653.75 labour days end to end

Fair share at target

£194,397

24% of the labour, valued at target

Against fair share

+£13,039

107% of its share of the target

Gross profit per labour day
£317
Break even £209Target £297

Each of the 653.75 days of labour the job uses makes £317.30 of gross profit, above both the £209 we need to break even and the £297 we aim for across the business. The work already done ran at £288 a day and what is left runs at £364. The gauge runs to £600 a day.

Weight it draws vs return it covers
Share of labour capacity used24%
Break even overhead covered36%
Profit target covered26%

It uses 24% of our labour over the year but covers 36% of the £570,000 of overheads we need to cover in that time, so it pulls more than its weight. The profit target for the period is £810,000.

The job was priced at 504.5 labour days and is now forecast at 653.75, an increase of 149.25 days, of which 112.75 are electrical. At £200 a day that extra labour is worth about £29,850, which is close to the whole £28,818 gap against the price.

LineChargePriced costCost to dateForecast costForecast margin
Plumbing & Heating£81,237.36£59,765.50£51,593.94£60,125.9426.0%
Electrical (net of savings)£194,202.50£115,504.50£54,023.30£137,874.5029.0%
HVAC (AC, vent and uplift)£179,636.67£93,396.00£49,933.77£99,483.7744.6%
Oldfield Lutron supply£107,309.40£95,968.40£22,490.93£95,968.4010.6%
Underfloor heating£37,279.00£37,279.00£32,778.50£37,279.000.0%
Fire, intruder, CCTV and facial recognition£56,245.00£34,925.00£8,952.57£34,925.0037.9%
Design£15,000.00£11,900.00£10,950.00£11,900.0020.7%
Preliminaries and skips£16,400.00£4,300.00£3,254.33£4,300.0073.8%
Utilities (power, water, gas)£9,870.00£9,487.07£9,487.07£9,487.073.9%
Testing and commissioning£3,600.00£2,000.00£0.00£2,000.0044.4%
Full contract£700,779.93£464,525.47£243,464.41£493,343.6829.6%

The £700 cost saving on the skips line is carried into the forecast final cost, which the model applies to the charge but omits from the cost; without it the forecast cost reads £494,043.68. All figures are net of the 5% VAT this job carries. Source: 2026-08 Priced vs Actual, the August application revised schedule and the payment schedule of 20 August 2026.

LCA0042-001LME · Prepared September 2026 · Costs to 31 August 2026 · Cash to 31 August 2026 · Confidential