Project performance report  ·  June 2026

6 Staveley Road

M&E Subcontract  ·  Leodis Developments Ltd

Project ref

LCA0042-001LME

Client

Usman Akbar

Contract value

£611,618

Value certified

£271,303

Status

In progress

Director's summary · June 2026

At a glance

Funded ahead, margin holding

Forecast profit

£216,384

34.5% · £18,410 above priced

Received ahead

£109,649

Funded ahead of work, no retention

Complete

44.4%

By value certified · finish Nov 2026

Labour efficiency

£456 a day

GP per labour day, above the £297 target rate

Certified by value 44.4%Cost incurred 50.0%

£271,303 certified · £340,315 of work still to bill · cost has edged just ahead of value certified

Profitability34.5% forecast, above the 31.6% price
Cash position£109,649 funded ahead, no retention
ProgrammeSix months in, finish forecast Nov 2026
Resource use£456 a day, above the target rate

Where the job stands today: what the client has paid, what has been certified as done, and what has been spent. The cash lead is read as timing rather than profit locked in, since it runs ahead of the work certified.

Performance scorecard · to date

Money in

£380,952

received, net of 5% VAT

Money certified

£271,303

value of completed work · 44.4%

Money spent

£204,921

cost to date · 50.0% of final cost

Funded aheadCash received runs £109,649 ahead of the work certified and there is no retention, so the surplus leads the secured position; the job is forecast to finish at a 34.5% margin.
1

Money in, certified and spent

As at 30 June 2026

The client has paid £400,000 to date, which is £380,952 once the five percent VAT of £19,048 is stripped out. Against that, the value of completed work stands at £271,303, or 44.4% of the £611,618 contract, and cost incurred is £204,921. Receipts therefore sit £109,649 ahead of the work certified, and with no retention held on this contract the works are funded well in advance of progress. On a cash basis the money in less the money spent leaves an indicative £176,031, but that figure is flattered by the payment lead and will narrow as later applications carry proportionally more cost than cash.

Cash, value and cost against their base

Cash received and value certified are shares of the £611,618 contract; cost incurred is a share of the £410,234 forecast final cost.

Money position

Contract value£611,618.02
Received, net of 5% VAT£380,952.38
Cumulative applied, ex VAT£343,088.95
Value of completed work£271,303.43
Cost to date£204,921.18
Received ahead of certified£109,648.95
Indicative cash margin to date£176,031.20
Retention heldNone

Receipts of £380,952 sit ahead of even the £343,089 applied to date, the client having funded the works in round sums ahead of the applications. The indicative cash margin is money in less cost, not certified profit, and is carried through to the resource section on that basis.

2

Resource efficiency to date

Labour consumed vs output

Gross profit to date

£176,031

£29,339 a month over six months

Fair share at target

£91,883

23% of the labour, valued at target

Above fair share

+£84,148

192% of its share of the target

Gross profit per labour day

£570
Break even £209 Target £297

Each of the 309 labour days drawn since January has returned £570 of gross profit, well clear of the £209 break even rate and the £297 target rate the whole business runs to. The gauge runs to £600 a day on this report to hold the rate.

Weight it draws vs return it covers

Share of labour capacity used23%
Break even overhead covered62%
Profit target covered43%

Draws 23% of the labour over the six months on site but covers 62% of the £285,000 break even overhead for the period. Profit target for the period £405,000.

Capacity used by trade · monthly

Electrical26 of 95 days · 27% used
Plumbing & Heating18 of 95 days · 19% used
HVAC8 of 38 days · 20% used

Average monthly days over the six months on site, against each trade's monthly capacity. Source: priced vs actual cost model, days used column.

MeasureAnnualPeriod
Resource share of capacity11.3%22.7%
GP vs break even30.9%61.8%
GP vs profit target21.7%43.5%
TradeDays usedUsed / mthCapacity / mth% monthly% annual
Plumbing & Heating108.018.094.619.0%9.5%
HVAC45.07.537.819.8%9.9%
Electrical153.025.594.627.0%13.5%
Trades306.051.0227.022.5%11.2%
Gross profit to date£176,031
Monthly GP average£29,339
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500

The three trades draw 306 labour days; a further 3 sit in preliminaries, testing and utilities, taking the total to the 309 carried in the resource summary. Gross profit is on the cash basis set out in section 1.

3

Cost incurred to date

Actual spend vs forecast

Of the £410,234 forecast final cost, £204,921 has been spent, so the job is 50.0% through its cost while 44.4% certified by value. Cost has edged just ahead of value as the latest actuals have landed, most of it on plumbing and heating, where two thirds of the cost is already committed. The left panel sets how far each trade is through its forecast cost; the right splits cost incurred from cost still to come.

Share of forecast cost spent, by trade

Plumbing & Heating66% of £55,350 spent
HVAC69% of £62,500 spent
Electrical53% of £97,225 spent
Other lump sum lines38% of £195,159 spent

Bar is the share of each group's forecast final cost already spent. Plumbing and heating is furthest through, which is why its margin is now largely fixed. The lump sum lines, led by the Oldfield supply, sit early on cost.

Cost incurred vs cost to complete

Cost to dateCost to complete

What the remaining work is expected to require and return over the five months to November, and the risks that could move the forecast before the job closes out.

Performance scorecard · remaining work

Cost to complete

£205,313

spend still to come

Labour days left

175

across 5 months to Nov 2026

Gross profit to earn

£44,441

£8,888 a month

Thinner back legThe remaining measured works are supply heavy, led by the Oldfield Lutron package, so the back leg earns a thinner margin than the work already banked.
1

Resource requirement vs output profit

Forward · 5 months to Nov 2026

Gross profit still to earn

£44,441

£8,888 a month over five months

Fair share at target

£52,037

15% of the labour, valued at target

Against fair share

(£7,597)

85% of its share of the target

Gross profit per labour day

£254
Break even £209 Target £297

Each of the 175 labour days still to come returns £254 of gross profit, above the £209 break even rate but short of the £297 target rate, as the remaining lines carry more supply than labour.

Weight it draws vs return it covers

Share of labour capacity used15%
Break even overhead covered19%
Profit target covered13%

Draws 15% of the labour over the five months to November but covers 19% of the £237,500 break even overhead for the period, so it still returns more overhead than the labour it uses. Profit target for the period £337,500.

Capacity used by trade · monthly

Electrical20 of 95 days · 21% used
HVAC9 of 38 days · 24% used
Plumbing & Heating4 of 95 days · 4% used

Filled shows the days Staveley needs each month; the rest is spare for other work. Figures are trade labour only. Total capacity is 2,724 days a year (P&H 1,135, Electrical 1,135, HVAC 454). Break even overhead is £570,000 a year; the profit target adds £240,000.

MeasureAnnualPeriod
Resource share of capacity6.4%15.4%
GP vs break even7.8%18.7%
GP vs profit target5.5%13.2%
TradeDays leftNeed / mthCapacity / mth% monthly% annual
Plumbing & Heating20.04.094.64.2%1.8%
HVAC45.09.037.823.8%9.9%
Electrical100.020.094.621.1%8.8%
Trades165.033.0227.014.5%6.1%
Remaining gross profit£44,441
Monthly GP contribution£8,888
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500

The three trades leave 165 labour days; a further 10 sit in preliminaries, testing and utilities, taking the total to the 175 carried in the resource summary.

2

Cost variances still to come

Priced vs forecast by trade

These are the costed trades whose forecast cost now differs from the price. Plumbing and heating has eroded heavily, but with two thirds of its cost spent the movement is close to locked rather than a live risk. Against it, electrical and heating ventilation are both forecasting ahead of price as their confirmed costs land under budget. Beyond the trades, preliminaries is the line to watch on data rather than performance, forecasting a final cost of only £2,600 against a £10,000 price, which lifts its margin to 85% and should be confirmed.

Trades eroding against price

TradeChargePriced marginForecast marginMovementCost spent
Plumbing & Heating£56,07018.0%1.3%-16.7 pts66%

Trades improving against price

TradeChargePriced marginForecast marginMovementCost spent
Electrical£184,04039.2%47.2%+8.0 pts53%
HVAC£139,75551.3%55.3%+3.9 pts69%

Cost spent is the share of each trade's forecast final cost already incurred. All three trades are more than half spent, so these movements are largely realised rather than forecast. Preliminaries is excluded here and carried as a data risk below.

3

Risks and data completeness

June 2026

Plumbing and heating margin at near breakeven

The plumbing and heating package is forecast to finish at £720 of gross profit, a 1.3% margin, against a priced 18.0%, as cost has run ahead of budget to a final £55,350. Two thirds of that cost is spent, so the position is close to fixed, but the remaining scope should be reviewed before further cost is committed.

Owner: Operations — action: review the plumbing and heating cost profile against the works still to complete

Preliminaries forecast well below its price

Preliminaries carries £17,450 of value and is forecasting a final cost of only £2,600 against a £10,000 price, which lifts its margin to 85% and adds about £7,400 to the whole job forecast. Until that final cost is confirmed the priced position is the safer reference, so the headline 34.5% should be read as carrying a small provisional element.

Owner: Commercial — action: confirm the forecast final cost for preliminaries

Cash received well ahead of value

Receipts of £380,952 net of VAT exceed the value of completed work by £109,649, and sit ahead of even the £343,089 applied, with no retention held. This is favourable for cash now, but future applications carry proportionally more cost than cash, most of it in the supply heavy Oldfield line, so the funding surplus is expected to narrow as the job matures.

Owner: Commercial — action: monitor cost to value and to cash as the programme completes

Work completion not recorded for several applied lines

Management and preliminaries, the basement and ground floor underfloor heating, the pool house provision and the MEP testing line are applied at 100% but carry no recorded work completion percentage, so their value of completed work reads as nil and the certified figure of £271,303 is understated. These should be confirmed to give an accurate completion figure.

Owner: Finance — action: obtain work complete percentages for the applied main contract lines

Two source documents not fully reconciled

The cost model values the scope at £626,618 against the £611,618 certified contract, the difference being the design package and the savings carried gross in the model. The cash and value figures in this report follow the application schedule; the cost, margin and forecast figures follow the priced vs actual cost model.

Owner: Commercial — action: tie the two schedules together line by line at the next valuation

The current position and the forecast for the remainder combined into a single view of how the job is expected to finish against the price.

Performance scorecard · at completion

Forecast final cost

£410,234

£18,410 under budget

Contract value

£626,618

cost model basis

Forecast gross profit

£216,384

34.5% margin

+2.9 pts vs 31.6% priceThe whole job view: performance to date plus the forecast for the remainder.
1

Performance forecast

Priced vs forecast at completion

This is how the job was priced set against where it is now forecast to land, taken from the priced vs actual cost model. The work was priced to return £197,974 of gross profit at 31.6%. On current costs it is forecast to deliver £216,384 at 34.5%, a favourable movement of £18,410. That comes from electrical and heating ventilation landing under budget, part offset by the plumbing and heating overrun, with a further £7,400 still resting on preliminaries. The chart shows where the movement comes from trade by trade.

Priced gross profit

£197,974

31.6% on £626,618

Forecast gross profit

£216,384

34.5% — electrical and HVAC confirmed

Gross profit variance

+£18,410

+2.9 pts vs price · favourable

Cost bridge

Priced cost budget£428,643.97
Forecast final cost£410,233.97
Cost variance vs budget£18,410.00 under
Cost incurred to date£204,921.18
Cost to complete£205,312.79
Value recovered per £1 of cost£1.32

Gross profit movement by trade

Cost saving, gross profit upCost overrun, gross profit down

Net movement +£18,410. The three costed trades net +£10,810; the other lump sum lines add a further +£7,600, chiefly the preliminaries cost revision, which remains provisional.

2

Cost and margin position

Priced vs forecast by trade

The table sets the priced cost and margin for each trade against the forecast. Heating ventilation is the strongest performer at 55.3%, with electrical close behind at 47.2% as its confirmed costs have come in under the priced budget. Plumbing and heating is the one trade eroding, down to 1.3% as cost has run ahead of price. The remaining lump sum lines, led by the Oldfield supply and the utilities, are grouped together as they are let as fixed packages rather than measured by trade.

TradeChargePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating£56,070£46,00018.0%£55,3501.3%-16.7 pts
HVAC£139,755£68,00051.3%£62,50055.3%+3.9 pts
Electrical£184,040£111,88439.2%£97,22547.2%+8.0 pts
Other lump sum lines£246,753£202,75917.8%£195,15920.9%+3.1 pts
Full contract£626,618£428,64431.6%£410,23434.5%+2.9 pts

Trades eroding against price

TradeChargePriced marginForecast marginMovement
Plumbing & Heating£56,07018.0%1.3%-16.7 pts

Trades improving against price

TradeChargePriced marginForecast marginMovement
Electrical£184,04039.2%47.2%+8.0 pts
HVAC£139,75551.3%55.3%+3.9 pts

The other lump sum lines carry a net improvement, chiefly the preliminaries cost revision, which remains provisional. Utilities water and gas carry small negative margins and are listed in the full cost model below.

3

Resource across the whole job

Labour used and to come vs output

Forecast gross profit

£220,472

£20,043 a month over eleven months

Fair share at target

£143,921

19% of the labour, valued at target

Above fair share

+£76,551

153% of its share of the target

Gross profit per labour day

£456
Break even £209 Target £297

Across the full eleven months each labour day returns £456 of gross profit, clear of the £209 break even rate and the £297 target rate the whole business runs to.

Weight it draws vs return it covers

Share of labour capacity used19%
Break even overhead covered42%
Profit target covered30%

Draws 19% of the labour over the eleven months but covers 42% of the £522,500 break even overhead for the period. Return runs well ahead of the resource consumed. Profit target for the period £742,500.

Capacity drawn by trade · monthly

Electrical23 of 95 days · 24% used
HVAC8 of 38 days · 22% used
Plumbing & Heating12 of 95 days · 12% used

Average monthly days over the eleven months from January to November, against each trade's monthly capacity. Whole job days are 128 plumbing and heating, 90 HVAC and 253 electrical, 471 across the trades.

MeasureAnnualPeriod
Resource share of capacity17.8%19.4%
GP vs break even38.7%42.2%
GP vs profit target27.2%29.7%
TradeDaysUsed / mthCapacity / mth% monthly% annual
Plumbing & Heating128.011.694.612.3%11.3%
HVAC90.08.237.821.6%19.8%
Electrical253.023.094.624.3%22.3%
Trades471.042.8227.018.9%17.3%
Forecast gross profit£220,472
Monthly GP average£20,043
Monthly break even hurdle£47,500
Monthly profit target hurdle£67,500

The three trades draw 471 labour days; a further 13 sit in preliminaries, testing and utilities, taking the total to 484. The resource gross profit of £220,472 is struck as the cash to date plus the remaining measured works less remaining cost, and so runs about £4,000 above the £216,384 priced margin because the client has paid ahead of the work certified.

LineChargePriced costCost to dateForecast costForecast margin
Costed trades
Plumbing & Heating£56,070.00£46,000.00£36,350.00£55,350.001.3%
HVAC (AC / Vent & Uplift)£139,754.62£68,000.00£43,050.00£62,500.0055.3%
Electrical (net of savings)£184,040.00£111,884.50£51,700.00£97,224.5047.2%
Other lump sum lines
Oldfield Lutron Supply£107,309.40£95,968.40£9,550.00£95,968.4010.6%
Underfloor Heating£37,279.00£37,279.00£32,778.50£37,279.000.0%
Fire subcontracted£21,700.00£13,136.00£1,758.36£13,136.0039.5%
Security / Intruder subcontracted£14,615.00£8,592.00£1,150.11£8,592.0041.2%
CCTV subcontracted£16,820.00£10,848.00£8,420.09£10,848.0035.5%
Wardrobe Facial Recognition subcontracted£3,110.00£2,349.00£314.43£2,349.0024.5%
Design£15,000.00£11,900.00£7,825.00£11,900.0020.7%
Testing & Commissioning£3,600.00£2,000.00£0.00£2,000.0044.4%
Utilities — Power£3,500.00£3,642.94£3,242.94£3,242.947.3%
Utilities — Water£2,370.00£2,770.00£2,570.00£2,970.00(25.3%)
Utilities — Gas£4,000.00£4,274.13£3,874.13£4,274.13(6.9%)
Preliminaries cost provisional£17,450.00£10,000.00£1,937.61£2,600.0085.1%
Full contract£626,618.02£428,643.97£204,921.18£410,233.9734.5%

Charge is the cost model contract value, which carries the savings gross and so reads £15,000 above the £611,618 certified contract. Electrical is shown net of the intruder, fire and gate access savings. Preliminaries is forecasting a final cost of £2,600 and is flagged pending confirmation.

RefDescriptionContract value% applied% work completeValue certified
Main contract
1.01Management & Preliminary Costs£15,700.00100.0%£0.00
1.02UFH — Basement£9,781.00100.0%£0.00
1.03UFH — Basement Upgrade Pipe Spacing£1,168.00100.0%£0.00
1.04UFH — Ground Floor£10,371.00100.0%£0.00
1.05UFH — Ground Floor Upgrade Pipe Spacing£1,168.00100.0%£0.00
1.06UFH — First Floor£13,726.00100.0%100.0%£13,726.00
1.07UFH — First Floor Upgrade Pipe Spacing£1,065.00100.0%100.0%£1,065.00
1.08AC & VENT£93,532.0060.0%62.0%£57,989.84
1.09Electrical Work£148,660.0060.0%50.0%£74,330.00
1.10Plumbing & Heating£51,500.0075.0%65.0%£33,475.00
1.11Sanitaryware Installation£0.00
1.12Provision to Pool House£2,110.0050.0%£0.00
1.13MEP Testing & Commissioning£3,600.0050.0%£0.00
Variations signed off
2.01Fire Opt 2£21,700.0050.0%17.5%£3,797.50
2.02Oldfield£107,309.4010.0%10.0%£10,730.94
2.03Skips£1,750.00100.0%50.0%£875.00
2.04Utilities — Power£3,500.00100.0%100.0%£3,500.00
2.05Utilities — Water£2,370.00100.0%100.0%£2,370.00
2.06Utilities — Gas£4,000.00100.0%100.0%£4,000.00
2.07Uplift Cast Effect Waste£2,460.00100.0%100.0%£2,460.00
2.08Electrical Review£57,650.0050.0%50.0%£28,825.00
2.09Intruder£14,615.0050.0%17.5%£2,557.62
2.10AC & VENT Uplift£46,222.6250.0%62.0%£28,658.02
2.11CCTV£16,820.0050.0%17.5%£2,943.50
2.12Wardrobe Facial Recognition£3,110.0050.0%17.5%£544.25
Savings
4.02Saving — Intruder(£8,130.00)
4.03Saving — Fire(£13,700.00)
4.04Saving — Gate Access(£440.00)
Contract total£611,618.0256.1% £271,303.43

Value certified is the contract value at the recorded work complete percentage. The main contract lines applied at 100% with no recorded work complete read as nil certified, so the £271,303 total is understated pending those percentages. There are no variations pending at this date; the savings on intruder, fire and gate access are already reflected in the contract value.

LCA0042-001LME  ·  Prepared July 2026  ·  Projected costs to 30 June 2026  ·  Confidential