Project performance report  ·  May 2026

6 Staveley Road

M&E Subcontract  ·  Leodis Developments Ltd

Project ref

LCA0042-001LME

Client

Usman Akbar

Contract value

£611,618

Value certified

£236,116

Status

In progress

Contract value

£611,618

Main, variations, net of savings

Value certified

£236,116

38.6% complete by value

Cost to date

£168,439

Priced versus actual cost model

Forecast margin

34.0%

£219,065 provisional, priced 30.2%

Received ahead of value

£106,973

No retention held

Cash and value against contract, cost against forecast56.1% · 38.6% · 39.5%
Cash received 56.1% of contract · value certified 38.6% of contract · cost incurred 39.5% of forecastIndicative gross profit earned £67,677

At the end of May 2026 the contract is 38.6% complete by value certified, with £236,116 of work valued against the £611,618 contract. The defining feature of this project is its funding profile. The client has paid £343,089, which is £106,973 ahead of the value of completed work, and no retention is held, so the works are financed well in advance of the work certified. Cost incurred stands at £168,439, giving an indicative gross profit earned of £67,677 on the work done so far. On the cost model the job was priced to return 30.2% and is currently forecast at 34.0%, though that forecast is still a little provisional because preliminaries carries no cost yet. The one trade moving the wrong way is plumbing and heating, where the forecast margin has fallen to 7.3% and warrants attention as the remaining scope completes.

1

Performance forecast

Priced vs forecast at completion

This is how the job was priced set against where it is now forecast to land, taken from the priced versus actual cost model. The work was priced to return £195,075 of gross profit at 30.2%. On current costs it is forecast to deliver £219,065 at 34.0%, a favourable movement of £23,990. Most of that comes from cost landing under budget on the heating ventilation and electrical trades, with a smaller part, about £6,000, still resting on preliminaries, which carries no forecast cost. The chart shows where the movement comes from across the three costed trades.

Priced gross profit

£195,075

30.2% on £645,078

Forecast gross profit

£219,065

34.0% — provisional forecast

Gross profit variance

+£23,990

+3.7 pts vs price · provisional

Forecast summary

Priced contract (cost model)£645,078.02
Priced cost budget£450,002.72
Forecast final cost£426,013.21
Cost variance vs budget£23,989.51 under
Cost incurred to date£168,438.50
Cost to complete£257,574.71
Forecast gross profit£219,064.81
Forecast margin34.0% provisional
Priced margin (reliable reference)30.2%

Gross profit movement by trade

Cost saving, gross profit upCost overrun, gross profit down

Costed trades only. The lump sum lines without forecast cost are omitted; design is held separately and excluded from the trade view.

The cost model values the scope at £645,078, which reconciles to the £611,618 certified contract through the design package (£15,000, settled separately and outside the applications), the agreed savings carried gross in the model, and a residual of about £3,810 in line grouping that is being tied out against the application schedule.

2

Cash and payment position

As at 31 May 2026

The client has applied and paid £343,089 against the contract, or 56.1% of the £611,618 value, while the value of completed work is £236,116, or 38.6%. The result is £106,973 received ahead of valuation. There is no retention mechanism on this contract, so every pound applied has been banked in full and nothing is held back for later release.

The main contract is 68.0% applied at £239,774, and the signed off variations are 36.7% applied at £103,315. The position is healthy for cash, but it carries a watch item. Several variation lines have been applied ahead of the work behind them, most notably Oldfield, the single largest line at £107,309, now applied and complete at 10%, so the application and the work have come back into step since April. The design package noted alongside this report sits outside these figures and has already been settled separately.

Applications and receipts

StreamContract value% appliedApplied & receivedValue complete
Main contract£352,381.0068.0%£239,774.20£156,018.88
Variations signed off£281,507.0236.7%£103,314.75£80,096.65
Savings(£22,270.00)
Total£611,618.0256.1%£343,088.95£236,115.53

Cash position

Contract value£611,618.02
Applied and received£343,088.95
Percentage applied56.1%
Value of completed work£236,115.53
Received ahead of valuation£106,973.42
Remaining unapplied£268,529.07
Retention heldNone
3

Cost and margin position

Priced vs forecast by trade

The cost model splits into three costed trades, plumbing and heating, the heating ventilation package, and electrical, with the remaining scope held as lump sum lines that are either priced as a unit or not yet costed. The table sets the priced cost and margin for each costed trade against the forecast. The charts split cost incurred from cost to complete and compare the priced cost against the forecast cost. Because the contract is largely let on lump sums, the analysis is held at trade level rather than the line by line view used on larger jobs.

TradeChargePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating£57,610£46,00020.2%£53,3947.3%-12.8 pts
HVAC£139,755£68,00051.3%£58,75158.0%+6.6 pts
Electrical£206,310£126,36038.8%£110,62646.4%+7.6 pts
Costed trades£403,675£240,36040.5%£222,77144.8%+4.4 pts

Cost incurred vs cost to complete

Cost to dateCost to complete

Priced cost vs forecast cost by trade

Priced costForecast cost

Costed trades exclude design, Oldfield, underfloor heating, the utilities and the other lump sum lines, which are listed in the full cost model below. The trade subtotal margin therefore differs from the whole contract forecast.

4

Value against cost

Earned position

This is the position the two workbooks unlock together. Work certified to the client stands at 38.6% of the contract, while cost incurred is 39.5% of the forecast final cost, so cost has edged just ahead of value as the latest actuals have come in. The indicative gross profit earned is £67,677. Because the contract lines and the cost lines are structured differently, this is a summary comparison rather than a line by line reconciliation.

The cash story sits on top of this. The client has paid 56.1% of the contract while 38.6% has been certified and 39.5% of forecast cost has been spent, so the project still holds a large funding surplus over both. That is a comfortable position, but it is partly a timing one. As the remaining applications are submitted they will carry the cost heavy back end of the job, so the surplus of cash over value is expected to narrow. The plumbing and heating margin and the last uncosted line, preliminaries, are the things that could move the earned position from here.

Percent complete — value vs cost

Indicative gross profit earned to date

£67,677

Value certified £236,116 less cost to date £168,439, on the cost model basis.

Cash received ahead of value

£106,973

Receipts £343,089 against value certified £236,116, with no retention held.

5

Margin movement by trade

Costed trades

The chart compares priced margin against forecast margin for each costed trade. Plumbing and heating is the one trade eroding, down from 20.2% to 7.3% as cost runs ahead of the priced budget on that package. The heating ventilation works and electrical are both forecasting ahead of price, at 58.0% and 46.4%, which is what pulls the costed trade subtotal up. The lump sum and uncosted lines are excluded here so that the comparison reflects real cost movement rather than placeholder margin.

Priced vs forecast margin by trade

Priced margin %Forecast margin %

Trades eroding against price

TradeChargePriced marginForecast marginMovement
Plumbing & Heating£57,61020.2%7.3%-12.8 pts

Trades improving against price

TradeChargePriced marginForecast marginMovement
Electrical£206,31038.8%46.4%+7.6 pts
HVAC£139,75551.3%58.0%+6.6 pts

The lump sum lines outside the three costed trades are excluded from this comparison, including preliminaries, which still carries no cost.

6

Variations and savings register

Signed off

Signed off variations add £281,507 to the contract and agreed savings reduce it by £22,270, for a net addition of £259,237 over the main contract. The savings are price reductions the client has taken on the intruder, fire and gate access scope, and are already reflected in the contract value. There are no variations pending at this date.

ItemValue% appliedStatus
Fire Opt 2£21,700.0050.0%Signed off
Oldfield£107,309.4010.0%Signed off
Skips£1,750.00100.0%Signed off
Utilities — Power£3,500.00100.0%Signed off
Utilities — Water£2,370.00100.0%Signed off
Utilities — Gas£4,000.00100.0%Signed off
Uplift Cast Effect Waste£2,460.00100.0%Signed off
Electrical Review£57,650.0050.0%Signed off
Intruder£14,615.0050.0%Signed off
AC & VENT Uplift£46,222.6250.0%Signed off
CCTV£16,820.0050.0%Signed off
Wardrobe Facial Recognition not banked£3,110.00Signed off, not in banked total
Variations signed off£281,507.0236.7% 
Saving — Fire(£13,700.00)Agreed reduction
Saving — Intruder(£8,130.00)Agreed reduction
Saving — Gate Access(£440.00)Agreed reduction

The schedule also lists a Boiler and Skid saving of £1,200 that is not extended into the savings total, so the agreed saving stands at £22,270 rather than £23,470. Worth confirming this is intended.

7

Risks and data completeness

May 2026

Forecast margin still rests on one uncosted line

The fire, security, CCTV and wardrobe facial recognition packages are costed at 85% of their value, a 15% margin, and the utilities now carry their actual cost, which removes most of the earlier distortion. Preliminaries alone remains, £15,700 of value, carrying no forecast cost and so a full margin. The priced margin of 30.2% is the reliable reference until that last line is costed.

Owner: Commercial — action: enter forecast cost for preliminaries, and confirm the 85% estimate on the security packages

Plumbing and heating margin erosion

The forecast margin on plumbing and heating has fallen from a priced 20.2% to 7.3% as cost runs ahead of budget on that package. This is on the costed trades and should be reviewed against the remaining scope before further cost is committed.

Owner: Operations — action: review the plumbing and heating cost profile against remaining works

Cash received well ahead of value

Receipts of £343,089 exceed the value of completed work by £106,973, with no retention held. This is favourable for cash now, but it means future applications carry proportionally more cost than cash. Oldfield, the largest single line at £107,309, is applied and complete at 10%, so application and work are in step, but the overall funding surplus should be monitored so the back end of the job does not erode the position.

Owner: Commercial — action: monitor cost to value and to cash as the programme matures

Work completion not recorded for several applied lines

Management and preliminaries, the basement and ground floor underfloor heating, the pool house provision and the MEP testing line are applied at 100% but carry no recorded work completion percentage, so their value of completed work reads as nil and the overall certified figure is understated. Wardrobe facial recognition shows a 50% application on the schedule that is not in the banked total and is held at nil here to match the receipts. These should be confirmed to give an accurate completion figure.

Owner: Finance — action: obtain work complete percentages and confirm the Wardrobe application status

Two source documents not fully reconciled

The cost model values the scope at £645,078 against the £611,618 certified contract. The difference is the design package at £15,000 settled separately, the savings carried gross in the model, and a residual of about £3,810 in line grouping. The contract, cash and value figures in this report follow the application schedule; the cost and margin figures follow the cost model.

Owner: Commercial — action: tie the two schedules together line by line at the next valuation

LineChargePriced costCost to dateForecast costForecast margin
Costed trades
Plumbing & Heating£57,610.00£46,000.00£34,393.50£53,393.507.3%
HVAC (AC / Vent & Uplift)£139,754.62£68,000.00£33,550.75£58,750.7558.0%
Electrical£206,310.00£126,360.00£46,626.24£110,626.2446.4%
Priced lump sum lines
Design settled separately£15,000.00£11,900.00£7,825.00£11,900.0020.7%
Oldfield Lutron Supply£107,309.40£95,968.40£9,550.00£95,968.4010.6%
Underfloor Heating£37,279.00£37,279.00£18,639.50£37,279.000.0%
Utilities — Water£2,370.00£2,770.00£2,370.00£2,770.00(16.9%)
Utilities — Gas£4,000.00£4,274.13£3,874.13£4,274.13(6.9%)
Utilities — Power£3,500.00£3,642.94£3,242.94£3,242.947.3%
Fire costed at 85%£21,700.00£18,445.00£3,227.88£18,445.0015.0%
Security (Intruder) costed at 85%£14,615.00£12,422.75£2,173.98£12,422.7515.0%
CCTV costed at 85%£16,820.00£14,297.00£2,501.97£14,297.0015.0%
Wardrobe Facial Recognition costed at 85%£3,110.00£2,643.50£462.61£2,643.5015.0%
Line without forecast cost
Preliminaries no cost£15,700.00£6,000.00£0.00£0.00100.0%
Full contract£645,078.02£450,002.72£168,438.50£426,013.2134.0%

Cost to date now reflects the actual spend recorded against each line. The fire, security, CCTV and wardrobe lines are forecast at 85% of their value; the utilities at their actual cost. Preliminaries alone is still to be costed.

RefDescriptionContract value% applied% completeValue certified
Main contract
1.01Management & Preliminary Costs£15,700.00100.0%£0.00
1.02UFH — Basement£9,781.00100.0%£0.00
1.03UFH — Basement Upgrade Pipe Spacing£1,168.00100.0%£0.00
1.04UFH — Ground Floor£10,371.00100.0%£0.00
1.05UFH — Ground Floor Upgrade Pipe Spacing£1,168.00100.0%£0.00
1.06UFH — First Floor£13,726.00100.0%100.0%£13,726.00
1.07UFH — First Floor Upgrade Pipe Spacing£1,065.00100.0%100.0%£1,065.00
1.08AC & VENT£93,532.0060.0%49.0%£45,830.68
1.09Electrical Work£148,660.0060.0%42.0%£62,437.20
1.10Plumbing & Heating£51,500.0075.0%64.0%£32,960.00
1.11Sanitaryware Installation£0.00
1.12Provision to Pool House£2,110.0050.0%£0.00
1.13MEP Testing & Commissioning£3,600.0050.0%£0.00
Variations signed off
2.01Fire Opt 2£21,700.0050.0%17.5%£3,797.50
2.02Oldfield£107,309.4010.0%10.0%£10,730.94
2.03Skips£1,750.00100.0%50.0%£875.00
2.04Utilities — Power£3,500.00100.0%100.0%£3,500.00
2.05Utilities — Water£2,370.00100.0%100.0%£2,370.00
2.06Utilities — Gas£4,000.00100.0%100.0%£4,000.00
2.07Uplift Cast Effect Waste£2,460.00100.0%100.0%£2,460.00
2.08Electrical Review£57,650.0050.0%42.0%£24,213.00
2.09Intruder£14,615.0050.0%17.5%£2,557.63
2.10AC & VENT Uplift£46,222.6250.0%49.0%£22,649.08
2.11CCTV£16,820.0050.0%17.5%£2,943.50
2.12Wardrobe Facial Recognition not banked£3,110.00£0.00
Savings
4.02Saving — Intruder(£8,130.00)
4.03Saving — Fire(£13,700.00)
4.04Saving — Gate Access(£440.00)
Contract total£611,618.0256.1% £236,115.53
LCA0042-001LME  ·  Prepared May 2026  ·  Confidential  ·  Forecast margin provisional pending cost pricing of preliminaries