Project performance report  ·  July 2026

6 Staveley Road

M&E Subcontract  ·  Leodis Developments Ltd

Project ref

LCA0042-001LME

Client

Usman Akbar

Contract value

£715,441

Value certified

£354,828

Status

In progress · finish Dec 2026

Director's summary · July 2026

At a glance

Below price, cash solid

Forecast margin is 28.1%, down from 34.5% in June. This is not general slippage: we have taken a fuller look at the electrical labour still to come, and HVAC has taken on a good deal of extra work. Forecast profit is (£14,991) lower than the June view.

Forecast profit

£201,393

28.1% · (£38,759) below priced

Complete

49.6%

by value certified · finish Dec 2026

Resource return

£283 a day

earned GP per labour day, just below the £297 target

Funded ahead

£67,079

received ahead of certified · working capital, no retention

Certified by value 49.6%Cost incurred 43.3%

£354,828 certified · £360,613 of work still to bill · value now runs ahead of cost, reversing the June position

Profitability28.1% forecast, below the 33.6% price
Cash position£67,079 funded ahead, no retention
ProgrammeFinish slipped to December 2026
Resource use£283 a day, just below the target rate

Where the job stands today: what the client has paid, what we have certified as done, and what we have spent. The client is paying ahead of the work certified, so we treat that lead as working capital, not profit.

Performance scorecard · to date

Money in

£421,906

received, net of 5% VAT

Money certified

£354,828

value of completed work · 49.6%

Money spent

£222,713

cost to date · 43.3% of final cost

Value leads costValue certified (49.6%) now sits ahead of cost spent (43.3%), a healthier shape than June. The client has paid £67,079 more than the work certified so far, and there is no retention held.
1

Money in, certified and spent

As at 31 July 2026

The client has paid £443,002 so far, which is £421,906 once the 5% VAT is taken off. Against that, the value of work completed is £354,828, or 49.6% of the £715,441 contract, and we have spent £222,713. So the client has paid £67,079 more than the work certified, and with no retention held the job is funded ahead of progress. Money in less money spent leaves £199,193, but that is working capital from being paid early, not profit earned, and it will unwind as the rest of the materials heavy work is billed.

Cash, value and cost against their base

Cash received59.0% of contract
Value certified49.6% of contract
Cost incurred43.3% of forecast cost

Cash received and value certified are shown against the £715,441 contract; cost is shown against the £514,048 we expect to spend in total.

Money position

Contract value£715,441.09
Received, net of 5% VAT£421,906.33
Value of completed work£354,827.63
Cost to date£222,712.92
Received ahead of certified£67,078.70
Indicative cash margin to date£199,193.41
Retention heldNone

The £199,193 is money in less cost, not profit earned. We treat it as working capital, and it is not used in the resource view on the expected outcome tab.

2

Progress and cost by trade

Completion vs spend

The job is 49.6% complete by the value of work signed off, against 43.3% of the expected cost spent, so value is ahead of cost overall. The bars below are all drawn to the same scale, so their length shows how big each trade is, and the gold line marks each trade's budget. Where a bar runs past its line, in red, that trade is forecast to finish over budget. Electrical is the clear concern at a quarter over; HVAC and plumbing and heating each run a little over; the grouped lump sum lines, the biggest single cost on the job, land on budget.

Overall completion 49.6% by value certifiedCost incurred 43.3%

Forecast cost against budget, by trade

Forecast within budget Forecast over budget Budget
Plumbing & Heating
Budget £62,376  →  forecast £68,076
Slightly over(£5,700) over
Electrical
Budget £115,065  →  forecast £143,676
Over budget(£28,611) over
HVAC
Budget £102,490  →  forecast £107,187
Slightly over(£4,697) over
Other lump sum
Budget £195,359  →  forecast £195,109
On budget£250 under
£0£50k£100k£150k£200k

All four trades are on the same scale, so bar length shows the real size of the spend. The gold line is each trade's budget, and the red shows how far the forecast runs past it. Electrical is the real overspend, a quarter over on the second biggest trade.

What the work still to come needs and brings in over the five months to December, and the risks that could shift the forecast before the job finishes.

Performance scorecard · remaining work

Cost to complete

£291,335

spend still to come

Labour days left

358

across 5 months to Dec 2026

Gross profit to earn

£69,278

£13,856 a month

Thin back legThe work still to come makes £193 of gross profit for each day of labour, below the £209 we need just to break even, because what is left leans on electrical labour and the materials heavy Oldfield line.
1

Cost to complete and remaining margin

Forward · 5 months to Dec 2026

Remaining revenue

£360,613

work still to bill

Remaining cost

£291,335

spend still to come

Remaining gross profit

£69,278

19.2% · £193 a labour day

2

Resource requirement to completion

Labour days by trade · Aug – Dec 2026

The job needs 358 more days of labour to finish. Plumbing and heating finishes by the end of September; HVAC and electrical run through to December. The table shows how many days each trade needs by month, and what share that is of the whole company's capacity for that trade. These numbers feed the company wide resource plan, where they are added to every other live job against our capacity of 2,724 days a year.

TradeAugSepOctNovDecTotalPeak capacity
Plumbing & Heating10.010.02011%
Electrical48.048.048.048.048.024051%
HVAC17.617.617.617.617.68847%
Trade days75.675.665.665.665.6348

A further 10 days of preliminaries and testing sit across the period, taking the total to 358. Peak capacity is the busiest month's days set against what we can do in that trade in a month (plumbing and heating 94.6, electrical 94.6, HVAC 37.8 days). Spreading the days evenly within each trade's window is a placeholder until we have a programme profile.

Share of firm capacity drawn · monthly peak

Plumbing & Heating (Aug – Sep)10 of 95 days · 11%
Electrical48 of 95 days · 51%
HVAC18 of 38 days · 47%

Amber where this one job takes a large share of a trade's monthly capacity, green where it leaves plenty free. Through to December it takes about half our electrical and HVAC capacity every month. That is exactly the sort of thing the company wide resource plan is there to catch across all live jobs.

3

Cost variances by trade

Priced vs forecast

These are the costed trades whose forecast margin now differs from the price. Electrical is the big mover, falling from 39.8% to 24.9% on the revised labour forecast. Plumbing and heating drops on its base work. HVAC gives back a little on the new work but keeps a strong margin, and the grouped lump sum lines are broadly flat.

TradeChargePriced marginForecast marginMovementCost spent
Plumbing & Heating£83,29625.1%18.3%(6.8 pts)61%
Electrical£191,27839.8%24.9%(14.9 pts)35%
HVAC£195,42347.6%45.2%(2.4 pts)44%
Other lump sum lines£246,75320.8%20.9%+0.1 pts43%
Full contract£716,75033.7%28.3%(5.4 pts)43%

Charge here is the cost model's contract value, which carries the savings gross and reads £1,309 above the £715,441 contract we work to. On that contract value the forecast is £201,393, a 28.1% margin.

4

Risks and data completeness

July 2026

Electrical labour forecast has risen sharply

Electrical is now forecast at 414 days of labour against about 261 priced, with 240 still to come, dropping the margin to 24.9% from 39.8%. This is the biggest single reason the job is now below its price, and it has pushed completion to December. Track the days used against site progress each month.

Owner: Operations. Action: check the electrical labour forecast against site output each week

Plumbing and heating base work is forecast to lose money

The base plumbing and heating line is forecast to finish below cost, and it is only pulled up to an 18.3% trade margin by the August variation. Two thirds of the cost is already spent, so the position is close to fixed, but it is worth a look before we commit any more cost.

Owner: Operations. Action: review the plumbing and heating work and cost still to come

New HVAC work just added, not started yet

The bigger HVAC variation adds £55,668 of value at a priced 38% margin but has not started on site, so its £34,490 of cost is all still to come. The forecast now carries its materials in full. Confirm it delivers at the priced margin as the work is done.

Owner: Commercial. Action: check the HVAC variation delivers at its priced margin

Two of the source sheets do not fully tie up

The contract value we work to is the balance variations sheet at £715,441; the cost model carries £1,309 more in its charge column. The difference is tiny and left as is for now, but the two should be tied line by line at the next valuation.

Owner: Commercial. Action: tie the balance variations and cost model sheets together

Where the job is now and the forecast for the rest, put together into one view of how it is expected to finish against the price, and the labour it uses from start to finish.

Performance scorecard · at completion

Forecast final cost

£514,048

costs to end July

Contract value

£715,441

balance variations basis

Forecast gross profit

£201,393

28.1% margin

(5.4 pts) vs 33.6% priceThe whole job view: where it is now plus the forecast for the rest, worked out as the value of the work less what it cost.
1

Priced vs forecast margin

At completion

This sets how the job was priced against where it is now forecast to finish, on the £715,441 contract. It was priced to make £240,152 of gross profit at 33.6%. On current costs it is forecast to make £201,393 at 28.1%, which is £38,759 worse, almost all of it electrical. The chart shows where the movement comes from, trade by trade.

Priced gross profit

£240,152

33.6% on the £715,441 contract

Forecast gross profit

£201,393

28.1%, eroded by electrical

Gross profit variance

(£38,759)

(5.4 pts) vs price · unfavourable

Cost bridge

Priced cost budget£475,289.47
Forecast final cost£514,048.36
Cost variance vs budget£38,758.89 over
Cost incurred to date£222,712.92
Cost to complete£291,335.44
Value recovered per £1 of cost£1.39

Gross profit movement by trade

Plumbing & Heating(£5,700)
Electrical(£28,611)
HVAC(£4,697)
Other lump sum+£250

Total movement (£38,759). Electrical is nine tenths of the fall; the other trades are small next to it.

2

Cost and margin by trade

Priced vs forecast
TradeChargePriced costPriced marginForecast costForecast marginMovement
Plumbing & Heating£83,296£62,37625.1%£68,07618.3%(6.8 pts)
Electrical£191,278£115,06539.8%£143,67624.9%(14.9 pts)
HVAC£195,423£102,49047.6%£107,18745.2%(2.4 pts)
Other lump sum lines£246,753£195,35920.8%£195,10920.9%+0.1 pts
Full contract£716,750£475,28933.7%£514,04828.3%(5.4 pts)

HVAC now carries the bigger August variation and its materials in full. On the £715,441 contract the forecast is £201,393 at 28.1%.

3

Resource across the whole job

Labour used and to come vs output · earned basis

Forecast gross profit

£201,393

£16,783 a month over twelve months

Fair share at target

£211,792

26% of the labour, valued at target

Against fair share

(£10,400)

95% of its share of the target

Gross profit per labour day

£283
Break even £209 Target £297

Each of the 712 days of labour the job uses makes £283 of gross profit, above the £209 we need to break even but short of the £297 we aim for across the business. The gauge runs to £600 a day.

Weight it draws vs return it covers

Share of labour capacity used26%
Break even overhead covered35%
Profit target covered25%

It uses 26% of our labour over the twelve months but covers 35% of the £570,000 of overheads we need to cover in that time, so it still pulls a little more than its weight. The profit target for the period is £810,000.

LineChargePriced costCost to dateForecast costForecast margin
Plumbing & Heating (incl. Aug variation)£83,296.05£62,375.50£41,501.00£68,076.0018.3%
Electrical (net of savings)£191,277.50£115,064.50£50,151.00£143,675.5024.9%
HVAC (incl. Aug variation)£195,422.83£102,490.00£46,997.39£107,187.3945.2%
Other lump sum lines£246,753.40£195,359.47£84,063.53£195,109.4720.9%
Full contract£716,749.78£475,289.47£222,712.92£514,048.3628.3%

Other lump sum lines cover the Oldfield supply, underfloor heating, the subcontracted security packages, preliminaries, design, testing and utilities. Charge carries the savings gross and reads £1,309 above the £715,441 contract we work to.

LCA0042-001LME  ·  Prepared August 2026  ·  Projected costs to 31 July 2026  ·  Confidential