Latest snapshot · Application 3, costs to 31 July 2026
Contract value
£101,742
Net of £1,652 discount, incl VO1
Applied to date
£45,415
44.7% of contract, to 31 July 2026
Net payable
£11,605
Application 3, after 5% retention
Cost to date
£34,214
To 31 July 2026, priced model
Forecast margin
£30,826
30.3% at completion, priced basis
Reports
Project reviews
Financial year 2025 — 2026
July 2026
Performance report · Application 3 · forecast 30.3% margin, £1,428 above the price · value applied £11,201 ahead of cost · £56,175 still to bill
Latest
Priced basis
Open report →
June 2026
Performance report · Application 2 · forecast 30.2% margin, just above the price · value applied £3,952 ahead of cost · £69,801 still to bill
Priced basis
Open report →
May 2026
Project review · first application · 52 days and £25,052 of materials left on a priced basis · £89,272 still to bill
Priced basis
Open report →
Further reviews will appear here as applications and costs are updated.