Performance report · August 2026
Tetley Hall Block E
M&E subcontract for C & AJ Marshall · LCA0001-011LME
Director's summaryOn price, on track
Forecast margin is 34.2%, up from 33.7% in July and well above the 25.9% we priced
August was the busiest month of the job so far: £64,518 more certified, taking it to 80% done, against £61,773 spent. Plumbing and heating and the underfloor heating came in cheaper than expected, which outweighed a little more cost on the electrics and HVAC.
Forecast profit
£183,923
34.2% · £44,495 above priced
Complete
80.1%
by value certified, finish October 2026
Resource return
£319 a day
forecast gross profit per labour day, above the £297 target
Applications to convert
£142,714
submitted, awaiting payment; App 5 due end September
Position
Profitability34.2% forecast, above the 25.9% price
Cash positionCost sits £4k ahead of cash, £143k converting
ProgrammeElectrical has 78 days left, more than a September finish allows
Resource use£319 a day, above the target rate
The decisionElectrical finish
The profit is safe. The decision is whether the electrics finish in September or run into October.
In July the plan was to finish by the end of September on 80 days of labour. The electricians used 32.5 days in August and the cost model now says 78 days are still needed. The project starting in October needs one or two electricians.
Cost model · the plan this report is built on
Two electricians, finish mid October
Two electricians at about 40 days a month clear the 78 days across September and the first half of October. It holds the team on Tetley for the first weeks of the October project.
Electricians2
Days left78
FinishMid Oct
The July target
Four electricians, finish in September
The July target assumed 47.5 days would be left after August; the model says 78. Doing all of that in September takes four electricians for the month and pulls them off other jobs.
Electricians4
Trade capacity82%
FinishEnd Sep
1 Performance to dateAs at 31 August 2026
80% certified, and cost runs only £4,412 ahead of the cash in, with £142,714 of applications converting
£0£537,730 contract
Received £266,219
Applied, unpaid £142,714
Retention held £21,523
Still to bill £107,273
Money in£266,219applications 1 to 4, net of retention
Money certified£430,456value of completed work, 80.1%
Money spent£270,631cost to date, 76.5% of final cost
This is timing, not the job earning less
Application 5 (£81,422) is due at the end of September on this job's terms and application 6 (£61,292) went in on 4 September. Once those are paid, money received moves well ahead of what we have spent. Half the £21,523 retention is claimable at practical completion, half at the end of the defects period.
1 Performance to dateForecast cost against budget
Every trade is still forecast to come in under its budget
80.1% complete by value against 76.5% of cost spent. The gap closed from ten points in July because £61,773 was spent against £64,518 certified, mostly electrical second fix materials landing. That is the shape we expected.
Plumbing & Heating
Budget £119,460, forecast £99,847
£19,613 under£88,216 spent, 88% through
Electrical
Budget £150,372, forecast £140,607
£9,766 under£79,727 spent, 57% through
HVAC
Budget £47,000, forecast £43,233
£3,767 under£40,333 spent, 93% through
Other lump sum
Budget £81,470, forecast £70,120
£11,350 under£62,355 spent, 89% through
2 Forecast, remaining workForward to November 2026
The last stretch earns £185 a labour day, below break even, because the profit is already in
Remaining revenue
£107,273
work still to bill
Remaining cost
£83,176
spend still to come
Remaining gross profit
£24,098
22.5% · £185 a labour day against the £209 break even
Most of what is left is electrical materials rather than labour, and it carries little margin. None of this is a worry: £159,825 of gross profit is already in the work signed off, at £358 a day, and the whole job comes out at 34.2%. There is simply not much more profit to be made from here.
Why it reads higher than July's 14.1%
August earned less than the July plan expected: £64,518 was certified for £61,773 of cost, so £2,745 of profit came in during the month rather than the £10,845 pencilled in, and the balance is still to earn.
2 Forecast, remaining workLabour days by trade · Sep – Nov 2026
About 130 labour days left, 78 of them electrical, with the electrics running into mid October
In August plumbing and heating used 30.75 days against a plan of 28, HVAC 12.25 against 10, and electrical 32.5 against the 40 the September target needed.
| Trade | Sep | Oct | Nov | Total | Peak capacity |
| Plumbing & Heating | 20.0 | 13.0 | 4.0 | 37 | 21% |
| Electrical | 40.0 | 33.0 | 5.0 | 78 | 42% |
| HVAC | 8.0 | 4.0 | | 12 | 21% |
| Trade days | 68.0 | 50.0 | 9.0 | 127 | |
Share of firm capacity, busiest month
Plumbing & Heating20 of 95 days 21%
Electrical40 of 95 days 42%
On its own the job takes under half of any trade. It is total electrical demand across all jobs that is worth watching through September and October.
2 Forecast, remaining workSep 2026 – Jan 2027 · before VAT
98% billed by the end of October, with £258,067 of cash still to come in by January
Billed by end October
98%
£104,952 of the £107,273 left to bill
Cash to completion
£258,067
received Sep to Jan, includes the first retention release
Retention drawn back
£13,443
first 2.5% at completion, £13,443 held to end of defects
Work billed and gross profit by month
CostGross profit
Cash received by month
Already applied (apps 5 and 6)Forecast from billingRetention release
2 Forecast, remaining workPriced against forecast, and since July
Every trade is ahead of its price. Since July, plumbing and the lump sums gained while electrical and HVAC gave a little back.
| Trade | Charge | Priced margin | Forecast margin | Movement | Since July | Cost spent |
| Plumbing & Heating | £160,567 | 25.6% | 37.8% | +12.2 pts | +2.7 pts | 88% |
| Electrical | £231,097 | 34.9% | 39.2% | +4.2 pts | (1.9 pts) | 57% |
| HVAC | £51,968 | 9.6% | 16.8% | +7.2 pts | (3.1 pts) | 93% |
| Other lump sum & variations | £94,098 | 13.4% | 25.5% | +12.1 pts | +4.6 pts | 89% |
| Full contract | £537,730 | 25.9% | 34.2% | +8.3 pts | +0.5 pts | 77% |
Plumbing and heating gained as its remaining days fell from 49.75 to 37 and its final materials came in lower. The lump sums gained because the Kensa underfloor heating was invoiced at £40,535 against the £47,762 priced.
Electrical gave back as its second fix days and materials rose a little, and HVAC as it needed four more days than expected. Read HVAC with caution: it was priced by a subcontractor as a lump sum with no labour and materials split.
2 Forecast, remaining workRisks and data completeness
Two amber risks: the electrical finish, and thin margin riding on materials
The electrics will not finish in September on two electricians
78 electrical days left against the 47.5 the September target would have left. The margin barely moves either way; what moves is where the team is in October.
Operations: decide between an October finish and adding electricians in September, and confirm the 78 days with the Lead Electrician.
Not much margin is left, and it rides mostly on materials
Only £24,098 of gross profit is left, and £39,808 of electrical second fix materials are still to land. If that cost runs over it comes almost straight off the bottom line.
Commercial: keep the electrical second fix materials cost in line with the forecast.
Cash is behind cost until the applications already in are paid
£4,412 behind, down from £10,424 in July now application 4 has been paid. Once application 5 lands, cash is well ahead of cost for the rest of the job.
Commercial: check application 5 is paid on time at the end of September.
The cost model has drifted from the July basis in four places
The CCTV variation, the underfloor heating price, the pending screed line and the design cost to date. This report holds all four to the July basis, so the movement it shows is real.
Finance: Cal to confirm the four points and correct the model for September.
3 Expected outcomeAt completion
Priced to make £139,427. Forecast to make £183,923, which is £44,495 better.
The gain is spread across all four cost groups as each comes in under budget, and is £2,450 more than July's, most of it the underfloor heating invoice and the plumbing and heating days.
Gross profit gain by trade
Plumbing & Heating+£19,613
Electrical+£9,766
HVAC+£3,767
Other lump sum+£11,350
Total gain against price+£44,495 · +8.3 pts
Cost bridge
Priced cost budget£398,302.14
Forecast final cost£353,806.77
Cost variance against budget£44,495.37 under
Cost incurred to date£270,631.17
Cost to complete£83,175.60
Value recovered per £1 of cost£1.52
3 Expected outcomePriced against forecast
A 34.2% job against a 25.9% price, with plumbing and the lump sums furthest ahead
| Trade | Charge | Priced cost | Priced margin | Forecast cost | Forecast margin | Movement |
| Plumbing & Heating | £160,567 | £119,460 | 25.6% | £99,847 | 37.8% | +12.2 pts |
| Electrical | £231,097 | £150,372 | 34.9% | £140,607 | 39.2% | +4.2 pts |
| HVAC | £51,968 | £47,000 | 9.6% | £43,233 | 16.8% | +7.2 pts |
| Other lump sum & variations | £94,098 | £81,470 | 13.4% | £70,120 | 25.5% | +12.1 pts |
| Full contract | £537,730 | £398,302 | 25.9% | £353,807 | 34.2% | +8.3 pts |
3 Expected outcomeLabour used and to come · earned basis
The job pays its way: £318.90 of gross profit for every labour day, above the £297 target
Forecast gross profit
£183,923
on 577 labour days end to end
Fair share at target
£171,501
21% of the labour, valued at target
Against fair share
+£12,422
107% of its share of the target
Gross profit per labour day
Break even £209Target £297
Weight it draws against the return it covers
Share of labour capacity used21%
Break even overhead covered32%
ReferenceFull cost model, condensed
Full cost model, priced against actual
| Line | Charge | Priced cost | Cost to date | Forecast cost | Forecast margin |
| Plumbing & Heating | £160,567.18 | £119,460.00 | £88,216.25 | £99,846.84 | 37.8% |
| Electrical | £231,097.00 | £150,372.23 | £79,726.59 | £140,606.69 | 39.2% |
| HVAC (MVHR & ventilation) | £51,967.56 | £47,000.00 | £40,333.08 | £43,233.08 | 16.8% |
| Other lump sum & variations | £94,097.86 | £81,469.91 | £62,355.25 | £70,120.16 | 25.5% |
| Full contract | £537,729.60 | £398,302.14 | £270,631.17 | £353,806.77 | 34.2% |